Allow the hot plug SATA drives and power supply modules to cool before touch- ing them.
•
Use a regulating uninterruptible power supply (UPS) to protect the server from power surges, voltage spikes and to keep your system operating in case of a power failure.
•
Install the heaviest server components on the bottom of the rack first, and then work up.
•
Server Precautions
• Review the electrical and general safety precautions in Chapter 4.
• Determine the placement of each component in the rack before you install the rails.
You should extend only one component at a time - extending two or more si- multaneously may cause the rack to become unstable.
•
Rack Precautions
• Ensure that the leveling jacks on the bottom of the rack are fully extended to the floor with the full weight of the rack resting on them.
• In single rack installation, stabilizers should be attached to the rack.
• In multiple rack installations, the racks should be coupled together.
• Always make sure the rack is stable before extending a component from the rack.
Warnings and Precautions!
SUPERSERVER
•Leave approximately 30 inches of clearance in the back of the rack to allow for sufficient airflow and ease in servicing.
•This product is for installation only in a Restricted Access Location (dedicated equipment rooms, service closets and the like).
•This product is not suitable for use with visual display work place devices accord- ing to §2 of the the German Ordinance for Work with Visual Display Units.
! |
! |