2 Site Planning

2.1 General

Before the start of an installation a survey should be conducted of the proposed area of the site(s). The survey personnel should be fully familiar with the details required to install the BridgeWave radio system.

2.2 Equipment Checklist

The survey team will need at least the following equipment:

Binoculars

GPS Navigation Device

Tape Measure

Site Survey Report Form

Level

2.3Line of Sight (LOS)

BridgeWave Wireless links require line­of­sight for proper operation. Fortunately, the links are relatively short and obstructions in the path can easily be identified. Binoculars can ease viewing in poor light conditions.

The planning should include an investigation into future building plans that could block the LOS path, and other long­term incremental obstructions such as trees. Intermittent obstructions such as aircraft at a nearby airport should also be considered.

The following table details the minimum clearance needed from obstacles near the path in order to ensure the radios will operate properly.

Path Length

Minimum Clearance

(meters)

(meters)

250

0.56

500

0.79

750

0.97

1000

1.12

1500

1.37

2000

1.58

Table 2­1: Minimum Clearance at Link Midpoint for various Path Lengths

580­00517, rev B

2

Image 8
Contents AR60X Wireless Ethernet Links Product Compatibility Copyright Notice & DisclaimerExport Control Safety Equipment Precautions Regulatory Information Table of Contents Prior Knowledge IntroductionPurpose of Manual Return Material Authorization RMA Contact InformationEquipment Checklist Site PlanningGeneral Line of Sight LOSLink Distance Antenna LocationCabling ­3 14­gauge DC power cable with crimp connectors Grounding & LightningEnvironmental Cabling Diagram Installation Equipment UnpackingEquipment Inventory Qty DescriptionInstallation Tools Antenna Mount Installation Tighten bolts SecurelyTighten bolts securely AR60X Installation Manual Antenna and Radio Installation ­9 Captive radio bolt detail ­10 Attaching the radio to the back of the antenna ­12 Elevation up/down adjustment Cable Installation Fiber CablingOptional Copper Ethernet Cabling Ground Cabling Ice Shield Canopy Installation IntroductionQty Description AR60X Installation Manual Antenna Alignment Auto Calibration States ­10 Quality Voltage Graph 10QUAL and RSL Test Cable Radio Link Status Indicators Connecting Network Equipment Network Port StatisticsAppendix a Troubleshooting Contact BridgeWave support to obtain a login accountAR60X Installation Manual Appendix B RSL Voltage vs. Distance DistanceStd. Limited Warranty & SW License Limited Hardware WarrantyLimitation of Remedy and Liability Provisions