American Power Conversion Redundant Switch operation manual Before You Begin

Page 5

Before You Begin

Safety and grounding information

Electrical

Hazard

Read the following information before installing or operating your APC Redundant Switch.

Do not work alone under hazardous conditions.

Check that the power cord, plugs, and sockets are in good condition.

To reduce the risk of electric shock when you can not verify grounding, disconnect the Redundant Switch from the power outlet before installing or connecting to other equipment. Reconnect the power cord only after all connections are made.

Do not handle any kind of metallic con nector before the power has been removed.

Use one hand, whenever possible, to connect or disconnect signal cables to avoid a possible shock from touching two surfaces with different electrical grounds.

Connect the equipment to a three-wire AC outlet (two poles plus ground) that is connected to appropriate branch circuit/mains protection (a fuse or circuit breaker). Connection to any other type of receptacle may result in a shock hazard.

To turn off and disengage the Redundant Switch, press and hold both UPS Off buttons for more than one second to switch the equipment off, then disconnect the Redundant Switch from the AC power outlet.

Pluggable equipment includes a protective earth conductor which carries the leakage current from the load devices (computer equipment). Total leakage current must not exceed 3.5 mA.

APC Redundant Switch: Installation and Operation Manual

1

Image 5
Contents APC Redundant SwitchThis manual is available in English on the enclosed CD Contents Page Before You Begin Part Number Description Quantity Pre-Installation ProceduresVoltage Source Input Load Output Available ModelsModel SU043 Model SU045-1 SU042-4Do not remove this deviceInstallation Following example shows how to attach the bracket for See Appendix a Rack-Mount Supplement Installation To the front of the Redundant Switch, connect Use two people to lift the Redundant Switch Turn on the equipment and Redundant Switch Both UPSs must be the same sine-wave model ConfigurationRestart the computer on which PowerChute plus is Function LED Display Description OperationYou can use a remotely operated Emergency Power Off EPO LED Display Status of Source Function Select LED Indicator. The three green FunctionFunction Status LED Indicator. The green Function Status Problem Possible Cause Corrective Actions TroubleshootingContinuously for capability to carry a load and ability to Specification SpecificationsSU043 and SU044-1 SU045 Appendix a Rack-Mount Supplement Type of Rack Hole Type Hardware Required Except as provided herein, APC makes no warranties Warranty and ServiceExpress or implied, including warranties of merchantability Fitness for a particular purpose. Some jurisdictions doWarranty and Service Life-Support Policy Page Radio Frequency Interference USA APC Worldwide Customer Support