Preventive Maintenance

8.5.4 Operation of the battery monitor

The operation of the battery monitor is performed from the user stack, the related parameters are:

Parameters in the user menu

Battery monitor test

This parameter is used for starting or interrupting a monitor test

Battery monitor reset

This parameter is used for resetting activated battery alarms

Battery monitor auto

This parameter is used for enabling or disabling of the automatic monitor test. Possible values are “OFF”, “3 months” (90 days), or “6 months” (180 days). When enabling is chosen the day counter will count starts. Please note that a change in setting will result in resetting of the day counter.

7OA0002 US rev. 04

User Guide Silcon DP300E Series 480V 240-320kVA

35

Image 35
Contents User Guide Silcon DP300E Series 480V 240-320kVA Silcon DP300E Series 480V 240-320kVA User GuideImportant Safety Instructions Table of Contents Display unit IntroductionIntroduction GeneralStart from stand-by Stop Start and Operating the External Service Bypass PanelStop stand-by Display shows Stop for complete power downSwitching off Silcon DP3240E DP3320E Starting up Silcon DP3240E DP3320E Start from complete power downLamp indication on bypass panel Single Utility Dual UtilityBypassing the UPS Action Display showsAction Switching the system from external bypass into normalSingle Utility UPS operationBypassing the parallel UPS system Emergency UPS not alive Press on the keyboard Press or on the keyboard until Following can be carried out on any UPS Isolating one UPS for service/maintenance Keyboard description OperationOperation Parameters Parameter Setting CommentsProgramming Parameters Programming ParametersKeys used for programming Programming example switch to bypass operation326 Programming of system configuration parameters438 346Programming example change charge voltage to Installation of new batteries Programming of battery monitorProgramming guide Description of settingsParallel programming/operation Programming parameters for advanced parallel operationProgramming example Highest Station No Other reasons for parallel operation alarm Parallel operation alarms GeneralAlarm texts conc. parallel operation Description MeasurementsReading Out Measurements Alarm messages AlarmsAlarms What To Do Alarm stackDisplaying the events stack Mode CommentsEvents logger Possible alarm Description Action Possible alarmsTemperature on static bypass System is locked in oper UPS has attempted 10 times Remote Display Operation Possible alarm DescriptionRemote Display Remote DisplayAdjusting contrast Fan Preventive MaintenancePreventive Maintenance BatteryActions Display shows Battery capacity testMonitor function Battery monitor testFunctionality of battery test Back-up timeBattery monitor auto Operation of the battery monitorBattery monitor test Battery monitor resetEconomy Operation Economy OperationInput System SpecificationsSystem Specifications Technical dataHow to Contact APC How to Contact APC