Programming Parameters

4.2.2Keys used for programming

NOTE:

The display accuracy is ±1-2%,

±1 digit.

4.2.3Programming example - switch to bypass operation

NOTE:

This is only to illustrate an example. Please see chapter 2.6 - 2.7 for further details.

Action

 

Display shows

1. Press

to enter parameter stack

 

 

 

Bypass operation

 

 

 

: NO

2.

Press

or

until

 

 

 

Bypass operation

3.

Press

until

: YES

 

4. Press

to store

 

5. Press

to exit

Bypass operation

To return to normal operation

Action

 

Display shows

6.

Press

to enter parameter stack

 

 

 

Bypass operation

7.

Press

or

: YES

until

 

 

 

Bypass operation

8.

Press

until

: NO

 

9.

Press

to store

 

10. Press

to exit

Normal operation

load power xx%

 

 

 

Programming of the other parameters can be performed in exactly the same way.

7OA0004 US rev. 02

User Guide Silcon DP300E Series 480V 400-500kVA

17

Image 17
Contents User Guide Silcon DP300E Series 480V 400-500kVA Silcon DP300E Series 480V 400-500kVA User GuideImportant Safety Instructions Table of Contents Introduction IntroductionGeneral Display unitStart from stand-by Stop Start and Operating the External Service Bypass PanelStop stand-by Display shows Stop for complete power downSwitching off Silcon DP3400E DP3500E Starting up Silcon DP3400E DP3500E Start from complete power downBypassing the UPS Single Utility Dual UtilityAction Display shows Lamp indication on bypass panelSingle Utility Switching the system from external bypass into normalUPS operation ActionBypassing the parallel UPS system Emergency UPS not alive Press on the keyboard Press or on the keyboard until Following can be carried out on any UPS Isolating one UPS for service/maintenance Keyboard description OperationOperation Programming Parameters Parameter Setting CommentsProgramming Parameters ParametersKeys used for programming Programming example switch to bypass operation438 Programming of system configuration parameters346 326Programming example change charge voltage to Installation of new batteries Programming of battery monitorParallel programming/operation Description of settingsProgramming parameters for advanced parallel operation Programming guideProgramming example Highest Station No Other reasons for parallel operation alarm Parallel operation alarms GeneralAlarm texts conc. parallel operation Description MeasurementsReading Out Measurements Alarms What To Do AlarmsAlarm stack Alarm messagesDisplaying the events stack Mode CommentsEvents logger Possible alarm Description Action Possible alarmsTemperature on static bypass System is locked in oper UPS has attempted 10 times Remote Display Possible alarm DescriptionRemote Display Remote Display OperationAdjusting contrast Preventive Maintenance Preventive MaintenanceBattery FanActions Display shows Battery capacity testFunctionality of battery test Battery monitor testBack-up time Monitor functionBattery monitor test Operation of the battery monitorBattery monitor reset Battery monitor autoEconomy Operation Economy OperationSystem Specifications System SpecificationsTechnical data InputHow to Contact APC How to Contact APC