External Connection

Terminal Blocks: X003/X004 (Anxiliary Contacts)

When switching Q001, Q002, Battery Breaker 1 or Battery Breaker 2 from “ON or 1” to “OFF or 0”, the anxiliary contact has to be open BEFORE the corresponding main contacts are opened. When switching Q001, Q002, Battery Breaker 1 or Battery Breaker 2 the opposite way from “OFF or 0” to “ON or 1”, the anxiliary contact has to close with a maximum delay of 0.5 seconds from the time the corresponding main contacts are closed.

This type of auxillary contact is called a “late make” contact. (This also means that it will “break early” when activated in opposite direction.)

This auxillary contact is also called “NORMALLY OPEN” (NO), because the auxillary contact will be open when the main contacts are open.

Please note that the above term “NORMALLY” has nothing to do with NORMAL UPS OPERATION MODE.

When switching Q003 from “OFF or 0” to “ON or 1”, the anxiliary contact has to open BEFORE the corresponding main contacts are closed. When switching Q003 the opposite way from “ON or 1” to “OFF or 0”, the auxillary contact has to close with a maximum delay of 0.5 seconds from the time when the corresponding main contacts are opened.

This type of anxiliary contact is called an “early break” contact. (This also means that it will “make late” when activated in the opposite direction.)

The auxiliary contact is also called “NORMALLY CLOSED” (NC), because the auxiliary contact will be closed when the main contacts are open.

Please note that the above term “NORMALLY” has nothing to do with NORMAL UPS OPERATION.

X005 (Output Relays)

Battery operation signals are received with a 30-second delay. This function is inactive during battery test. Common fault relay facility is programmable (standard factory setting: 10 sec.) See APC Silcon User Guide for details.

Maximum nominal voltage on contact circuits is 277VAC. If two different phases are involved, maximum phase to neutral voltage should be below 160VAC. Please note that phase L1 is already present on the System Integration Interface board, supplied from the Service Bypass Panel. Therefore, if a phase is needed for alarm or signal purposes, Phase L1 should be used.

 

990-4059

 

 

Installation Guide APC Silcon 480kW 400V UPS

11

Image 11
Contents 480kW 400V UPS Installation Guide Thank You Installation Guide APC Silcon 480kW 400V UPSSafety Symbols used in this manual Tools IntroductionIntroduction Tools and EquipmentUnpacking UnpackingHeight mm Width mm Depth mm 480kW 1800 1900 InstallationInstallation Requirements on Site2 1600mm Cabinet for 480kW Isolation Transformer Footprint1 1900mm Cabinet for 480kW UPS Right side view Connecting the UPSExternal Connection External ConnectionSystem Integration Interface External Connection Connections X005 Output Relays Terminal Blocks X003/X004 Anxiliary ContactsParallel Board Parallel BoardExternal Control Cables Power CablesRelays Relay BoardRelay Board/Relay Functions Relay Number Message Alarm-trigging EventsSee .2 System configuration Communication Interface Board Connecting of APC Silcon Tripel Chassis Monitoring Port Safety WarningsAPC Silcon Triple Chassis Product DescriptionIf the LED is… Then the Silcon Triple Chassis… Optional Power InputInstalling Management Peripherals LEDsDaisy-chaining the APC Silcon Triple Chassis Installing Management Peripheral CardsOrder of Management Peripheral Cards Management Peripheral Priority Position CardManagement Peripheral Draw mA If Problems Persist TroubleshootingProblem Possible Cause Solution Product Specifications Monitoring Port Pin Assignments External Connection Specification Power, Physical, and Environmental SpecificationsImportant Safety Instructions APC Silcon Battery CabinetsSilcon Battery Breaker Box/Fuse-boxInstallation of Batteries Battery Breaker Box Circuit Ampere Connection Max Dimensions Weight Rating CableAPC Battery Breaker Box Connection Diagram 120-480kW HxWxD mmExternal Connection Parameters Parameter Setting CommentsProgramming Parameters Programming ParametersProgramming Keys Programming Example Switch to Bypass Operation System ConfigurationSystem Configuration Parameters password protected Programming Example Change Charge Voltage to Programming Parameters Programming Parameters for Advanced Parallel Operation Description of SettingsProgramming example Battery MonitorProgramming Parameters Service Bypass Panel for Single Operation Options/AccessoriesOptions/Accessories Options/Accessories Lamp indication On Service Bypass PanelAction Display showsLamp indication On Servive Bypass Panel Switching from External Bypass to Normal UPS OperationService Bypass Panel for Parallel Redundant Operation Two Parallel Systems with Service Bypass Panel Options/Accessories Options/Accessories Action H002a Lamp indication On Service Bypass Panel Following can be carried out on any UPS Switching Back to Normal Parallel/Redundant Operation Isolating One UPS for Service/MaintenanceIntersystem Synchronization Unit ISU Intersystem Synchronization UnitIntersystem Synchronization Unit System ISU System Standard Short-haul RS232 Modem Async Remote DisplayExtension of Remote Display Communication Distance Pin Connections for cable from host to ME800A-R2 Host Connections Without ConverterHost DTE Remote Display DTE Connections With ConverterRemote Display Cables Remote Display Power SupplyRemote Display Use Communication FaultRemote Display Setting Alarms540kVA 480kW 1800 1400 2550 Height Width Depth WeightIsolation Transformer IsolationExample of Transformer Configuration Yyno 1000 200 Connecting Isolation TransformerExternal External PE 540kWOptions/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories Dimensions / Weight System SpecificationsSystem Specifications Technical DataAPC Silcon Series Limited Factory Warranty WarrantyWarranty Appendix Installation Planning DataAppendix Appendix APC Denmark How to Contact APCHow to Contact APC APC Corporate