Cable knockout plates are provided at the bottom of the 100 kVA UPS, and at the top and bottom of the 150/225 kVA UPS. (Older models of the G8000 150/225 kVA UPS do not come equipped with an upper knockout plate.) The recommended hole locations are illustrated in Figure 11.3, 11.4, and 11.5.

The five (5) holes must be punched during installation. The dashed rectangle indicates the UPS opening behind the knockout plates.

plate #1

plate #2

0.8”

3” Dia.

0.8”

2” Dia.

AC INPUT

BYPASS AC OUTPUT BATTERY CONTROL

 

WIRES

FIGURE 11.3 - Bottom CABLE KNOCKOUT PLATES 100 kVA (T80S3K10KK6XS2H)

plate #1

plate #2

plate #3

0.8”

 

4” Dia.

 

2” Dia.

 

4” Dia.

 

 

0.4”

 

 

AC INPUT

BYPASS

AC OUTPUT

BATTERY CONTROL

 

 

 

WIRES

FIGURE 11.4 - bottom CABLE KNOCKOUT PLATES 100 kVA (T80S3K10KK6XSNH); 150/225 kVA

FIGURE 11.5 - Top Access KNOCKOUT PLATE (If available - 150 and 225 kVA only)

32

G8000 Series Installation and Operation Manual

Image 40
Contents G8000 Series Page Document November Qualified Personnel only Uninterruptible Power System UPS Purpose Toshiba’s Customer Support CenterToshiba Customer Support Center Toshiba International CorporationTable of Contents 11.3 Introduction Symbols General Safety InstructionsProhibited Symbol indicates do not take action Signal Words Qualified PersonnelImportant Safety Instructions Factory Authorized PersonnelSafety Precautions DisclaimerGeneral Maintenance Keep the area arround the UPS cleanTransporting/Unpacking Do not tilt the UPS more than 10 from upright positionDo not transport, move, store, or place the UPS on its side Avoid vibration or shock exceeding 0.5GInspection/Storage Install the UPS in a controlled environment Installation PrecautionsKeep the Specified Clearance around the UPS Do not install the UPS where water may fall on it Do not block air ventsInstallation Precautions Environment standardPage Wiring/Connection Perform wiring and connections with correct polarityConnect only one 1 ground wire to the earth ground terminal Follow the torque criteria for tightening screwsFor 100, 150, 225KVA GND 150/225 kVA UPS Warning Labels Weight and Dimensions Model Unit Shipping300 kVA UPS Exterior Dimensions Inches Transporting Transporting By Crane 8.5 show examples of acceptable and unacceptable operationsTransporting By Forklift Transporting UPS by ForkliftOperating Precautions Storage/Operating EnvironmentPage Qualified Personnel only Maintenance PrecautionsQualified Personnel shall Do not dispose of the batteries in a fire DisposalDo not open or mutilate the batteries Installation Unpacking UPS ClearanceAnchor Bolt Installation Detail Anchor BoltsUPS Wiring External Wiring DiagramTerminal Blocks and Power Cables Block Number Cable Size Tightening TorqueRecommended Cable Size & Tightening Torque for 150 kVA UPS AC Input Bypass AC Output Battery Control Wires CRA-1/OL Plate #4 Bus Number Cable Size Tightening Torque Terminal Bus # RecommendationExternal Breakers Grounding WireBe sure to ground the UPS as specified G8000 100 kVA G8000 150/225 kVA Control Wires Signal Name Operation10 Connection Between UPS, Battery Cabinet & Bypass Breaker Grounding Configuration 11 Grounding Configuration with Input Neutral GroundedGrounding Configuration without input neutral Recommended Configuration for delta-inputGrounding Configuration with corner-grounded delta-input 15 Grounding Configuration with CORNER-GROUNDED DELTA-INPUTUPS Specifications General SpecificationMechanical Specification Terms Specification RemarksRated Capacity 150 kVA 225 kVA 300 kVA Electrical Specification Do not open the front coverOperator Interface UPS may not respond if the button press is too shortKey-Switch and Buttons Graphic display Panel KEY-SWITCH/OPERATING Buttons13.2 LCD/LED Indicators Graphic display Panel LCD/LED INDICAtorsLCD Indicators Name DescriptionNormal Display AC-VO AC- I O 50%Volt Freq .0Hz 50%AC I/P-V Freq .0Hz BYP I/P-V Freq .0HzDC-V BATT-V BATT- I 0A 32TIMFault Display 09-09-06LCD Scroll AbbreveationsEpo and Control Power supply operating switches Operating the UPSPre-operational Check Operation TypesPerform the pre-operational check before operating the UPS Startup Procedures Procedure to start the UPS is shown in StepsAC Vo 480 AC Io 50% Switch Power Supply UPS→Bypass Bypass LED is onStop Complete Shutdown DC-V 0 BATT-V 0 BATT-I 0 aChanging Between Float Charge and Equalize Charge Make sure that the Float Charge LED is onMake sure that the Equal Charge LED is on Emergency Power Off EPO TroubleshootingTypes of Errors Faults and Warnings Data Screen 09-09-06LCD Fault & Warning Displays Fault DisplayFault Messages Over HeatLCD Message Indication Description LCD Scroll w/ faults or warnings Button functionsContact Toshiba in the event of malfunction or fault Restoring UPS OperationDo not attempt to modify or relocate the UPS Do not open the front and/or rear panelsPage Page Industrial Division
Related manuals
Manual 74 pages 20.32 Kb Manual 1 pages 30.84 Kb