Toshiba 300 KW Transporting, Do not tilt the UPS more than 10 from upright position

Page 27

8 Transporting

WARNING

When transporting the UPS by crane, follow the SPECIFIED WORK PROCEDURE. The suspension wire angle should be less than 60°.

The UPS falling or overturning may cause crushing, trapping or other personal injuries.

DO NOT tilt the UPS more than 10° from upright position.

Tilting the UPS more than 10° may cause crushing, trapping or other personal injuries.

CAUTION

DO NOT transport, move, store, or place the UPS on its side.

Excessive force applied from heavy components inside may damage the UPS.

Avoid vibration or shock exceeding 0.5G.

Failing to observe this precaution may cause damage to the UPS.

DO NOT allow the UPS to suffer shock or impact when unpacking.

Tools used to remove packaging materials may cause damage to the

UPS.

DO NOT install the UPS where water may fall on it.

Water may cause electrical shock, personal injury or UPS failure.

DO NOT push or pull on the sides of the packaging.or the UPS to move it. Always use a crane, forklift, or pallet jack for transporting and positioning the UPS.

Pushing/pulling on the sides of the unit to move it may result in damage to the UPS. (See Figure 4.1 Exterior Handling label.)

The UPS may be packed in a crate for extra protection during transportation. Avoid impact or vibration against the UPS during transportation. DO NOT expose the UPS directly to water.

G8000 Series Installation and Operation Manual

19

Image 27
Contents G8000 Series Page Document July Qualified Personnel only Uninterruptible Power System UPS Toshiba International Corporation PurposeToshiba’s Customer Support Center Toshiba Customer Support CenterTable of Contents 11.4 Introduction General Safety Instructions SymbolsProhibited Symbol indicates do not take action Qualified Personnel Signal WordsFactory Authorized Personnel Important Safety InstructionsDisclaimer Safety PrecautionsDo not tilt the UPS more than 10 from upright position General MaintenanceKeep the area arround the UPS clean Transporting/UnpackingAvoid vibration or shock exceeding 0.5G Do not transport, move, store, or place the UPS on its sideInspection/Storage Installation Precautions Install the UPS in a controlled environmentKeep the Specified Clearance around the UPS Do not block air vents Do not install the UPS where water may fall on itEnvironment standard Installation PrecautionsConductor Routing and Grounding Metal Conduit is not AN Acceptable GroundFollow the torque criteria for tightening screws Wiring/ConnectionPerform wiring and connections with correct polarity Connect only one 1 ground wire to the earth ground terminalFor 100, 150, 225KVA GND 150/225 KVA UPS Warning Labels Model Unit Shipping Weight and Dimensions300 KVA UPS Exterior Dimensions Inches Transporting 8.5 show examples of acceptable and unacceptable operations Transporting By CraneTransporting UPS by Forklift Transporting By ForkliftStorage/Operating Environment Operating PrecautionsPage Maintenance Precautions Qualified Personnel onlyQualified Personnel shall Disposal Do not dispose of the batteries in a fireDo not open or mutilate the batteries Installation UPS Clearance UnpackingAnchor Bolts Anchor Bolt Installation DetailExternal Wiring Diagram UPS WiringBlock Number Cable Size Tightening Torque 11.1 100 kVA Terminal Blocks and Power CablesAC Input Bypass Input AC Output Battery Block Number Cable Size Recommended Fastener Torque YA36LBus Number Cable Size Recommended Fastener Torque Bottom Cable Knockout Plates for 100 KVA T80S3K10KK6XS2H UPS Power Cable Knockout PlatesTerminal Knockout Plates for the 300 KVA UPS Plate #2 Plate #3Grounding Wire External BreakersBe sure to ground the UPS as specified G8000 100 kVA G8000 150/225 kVA Signal Name Operation Control Wires11 Connection Between UPS, Battery Cabinet & Bypass Breaker 12 Grounding Configuration with Input Neutral Grounded Grounding ConfigurationRecommended Configuration for delta-input Grounding Configuration without input neutral16 Grounding Configuration with CORNER-GROUNDED DELTA-INPUT Grounding Configuration with corner-grounded delta-inputTerms Specification Remarks UPS SpecificationsGeneral Specification Mechanical SpecificationNominal Capacity 150 kW 225 kW 300 kW Do not open the front cover Electrical SpecificationUPS may not respond if the button press is too short Operator InterfaceGraphic Display Panel KEY-SWITCH/OPERATING Buttons Key-Switch and ButtonsGraphic Display Panel LCD/LED Indicators 13.2 LCD/LED IndicatorsName Description LCD Indicators50% Normal DisplayAC-VO AC- I O 50% Volt Freq .0Hz32TIM AC I/P-V Freq .0HzBYP I/P-V Freq .0Hz DC-V BATT-V BATT- I 0A09-09-06 Fault DisplayAbbreveations LCD ScrollOperating the UPS EPO and Control Power Supply Operating SwitchesOperation Types Pre-operational CheckPerform the pre-operational check before operating the UPS Procedure to start the UPS is shown in Steps Startup ProceduresAC Vo 480 AC Io 50% Bypass LED is on Switch Power Supply UPS→BypassStop DC-V 0 BATT-V 0 BATT-I 0 a Complete ShutdownMake sure that the Float Charge LED is on Changing Between Float Charge and Equalize ChargeMake sure that the Equal Charge LED is on Troubleshooting Emergency Power Off EPOTypes of Errors 09-09-06 Faults and Warnings Data ScreenFault Display LCD Fault & Warning DisplaysLCD Message Indication Description Fault MessagesLCD Message Indication Description Reset LCD Scroll w/ faults or warningsDo not open the front and/or rear panels Contact Toshiba in the event of malfunction or faultRestoring UPS Operation Do not attempt to modify or relocate the UPSPage Page Industrial Division