American Dryer Corp ML-75HS installation manual

Page 21

3.Multiple Dryer (common) Venting

If it is not feasible to provide separate exhaust ducts for each dryer, ducts from individual dryers may be channeled into a "common main duct." The individual ducts should enter the bottom or side of the main duct at an angle not more than 45º in the direction of air flow and should be spaced at least 38-1/4 inches apart. The main duct should be tapered, with the diameter increasing before each individual duct (10-inch minimum) is added.

IMPORTANT: No more than four (4) dryers should be connected to main common duct.

The main duct may be any shape so long as the minimum cross sect is provided. The illustration on page xx shows the minimum cross section area for multiple dryer round or square venting. These figures must be increased 10 square inches when rectangular main ducting is used, and the ration of duct width to depth should not be greater than 3-1/2 to 1. These figures must be increased in proportion if the main duct run from the last dryer to where it exhausts to the outdoors is unusually long (over fifteen [15] feet) or has numerous (more than two [2] elbows in it). In calculating duct work size, the cross section area of a square or rectangular duct must be increased twenty (20) percent for each additional fifteen (15) feet. The diameter of a round exhaust must be increased ten (10) percent for each additional fifteen (15) feet. Each 90º elbow is equivalent to an additional thirty (30) feet and each 45º elbow is equivalent to an additional fifteen (15) feet.

IMPORTANT: For extended duct work runs, the cross section area of the duct work can only be increased to an extent. Maximum proportional duct work runs cannot exceed fifteen

(15)feet with two (2) elbows. When the duck work approaches the maximum limits as noted in this manual, a professional HVAC firm should be consulted for proper venting. HVAC should be consulted for proper venting information.

The duct work should be smooth inside with no projections from sheet metal screws or other obstructions which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL duct work joints must be taped to prevent moisture and lint from escaping into the building. Inspection doors should be installed at strategic points in the exhaust duct work for periodic inspection and clean-out of lint from the duct work.

NOTE: Where the exhaust passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches larger (all the way around) than the duct. The duct must be centered within this opening.

a.Outside Duct Work Protection

1)To protect the outside end of horizontal duct work from weather, a 90º elbow bent downward should be installed where the exhaust exits the building. If the duct work travels vertically up through the roof, it should be protected from the weather by using a 180º turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and the nearest obstruction.

IMPORTANT: DO NOT use screens or caps on the outside of opening of exhaust duct work.

17

Image 21
Contents ML-75HS Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check of Replacement Important Information SectionDamage plastics or rubber and also may be a fire hazard Safety PrecautionsFrom the Machine to Allow Access for Cleaning Specifications SPECIFICATIONS/COMPONENT IdentificationSpecifications Dryer Front View Component IdentificationDryer Rear View Location Requirements Installation ProceduresBefore Starting the Dryer UNPACKING/SETTING UPDryer Enclosure Requirements Fresh AIR Supply Horizontal Venting Exhaust RequirementsReduced Anywhere Down Stream of the Dryer Page Page Page Electrical Requirements Electrical InformationMLG-75 Gas MLS-75 Steam Electric Models Only MLE-75 ElectricGrounding Single-Phase 1Ø Electrical Connections Leads Page Phase Wiring Connections/Hookup Reversing Models Only Electrically Heated Models only Gas Supply GAS InformationInch N.P.T Gas ConnectionsInch N.P.T. minimum 200,000 Natural GasPiping/Connections Steam Information Steam Requirements High Pressure Installation InstructionsPage Compressed Air Supply Air Pressure Steam Damper System Operation Steam Damper Air Piston Flow Control Operation Adjustment Preparation for OPERATION/START-UP Gas Dryers Preoperational TestsElectrically Heated Dryers Preoperational Instructions Shut Down Instructions SERVICE/PARTS Information ServiceParts Warranty Information Returning Warranty CardsReturning Warranty Parts Page Routine Maintenance CleaningOperational running hours per day Days AdjustmentsMicroprocessor computer Board Procedure for Functional Check Replacement ComponentsPage Page Timing Legend Reversing Timer SPIN/DWELL AdjustmentsData Label Technical InformationSerial Number ADC113001