Hearth

A hearth is not mandatory but is recommended for aesthetic purposes. We recommend a noncombustible hearth which projects out 12” (305 mm) or more from the front of the fireplace. The hearth cannot exceed 1¹⁄₂” (38mm) in height from bottom of fireplace for ease of door accessibility. (Fig. 5)

Cold climate installation recommendation: When installing this unit against a non- insulated exterior wall or chase, it is

mandatory the outer walls be insulated to conform to applicable insulation codes.

If a vapor barrier is used it can not come into contact with fireplace.

Framing and Finishing

1.Choose the unit location.

2.The unit is shipped with four (4) nailing flanges mounted to the sides near the front corners. (Fig. 5)

3.Frame the fireplace with a header across the top of the standoff. (Fig. 6) It is very important to allow for the finished wall face along with marble, tiles or any other noncombustible face finish material desired when setting the depth of the framing.

Valve Box

Assembly

Bend

Line

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3"

 

 

 

 

 

 

 

 

 

3"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(76 mm) Min.

 

(76 mm) Min.

1���"

 

(38 mm)

 

Max. Hearth Height

FP1775

Fig. 5 Nailing flanges.

4.Attach the fireplace nailing flanges to the frame as shown in Figure 5.

5.The gas components are located in the control panel assembly attached to the right side of the unit. (Fig. 5)

Chateau™

3" (76mm)

3"

FP1560

(76mm)

 

Fig. 6 Fireplace framing.

6.The U-channel located on the top of the unit as well as the nailing flanges on the sides that were men- tioned in Step 1, are designed to accommodate non- combustible board (recommended Dura-Rock). They are positioned 1” (25mm) back from the face of the unit. NOTE: The U-channel depth can be adjusted by loosening the hex nut inside the channel.

If marble, tile or any other noncombustible decora- tive face finish material is desired, a 3” (76 mm) wide noncombustible board (recommended Dura-Rock) is to be nailed to the nailing flanges on both sides of the unit. Also, 12” (305 mm) of noncombustible board is to be nailed to the front face of the U-chan- nel and the top framing member above the standoff.

Combustible material can then be brought to the outside edges of the noncombustible board installed earlier. Any noncombustible decorative face finish could be brought to the sides and top of the unit and can cover the framing and sheet rock. If a decora- tive facing is not desired, then the noncombustible boards must be double thickness and brought flush with the face of the unit.

Final Finishing

Noncombustible materials such as brick or tile may be brought to the edges of the face of the appliance.

7

Image 7
Contents What to do if YOU Smell GAS INSTALLER/CONSUMER Safety InformationTable of Contents Certified To Installation & Operating InstructionsPlease Review the Following Carefully Clear of ALL Obstructions Requirements for the Commonwealth of Massachusetts Gas Equipment Venting System not Provided Fireplace Dimensions DVT38IN Clearance to Combustibles Locating Your FireplaceMantels Framing and Finishing HearthFinal Finishing High Elevations Gas Line InstallationGas Specifications Gas Inlet and Manifold PressuresControl System Control System InstallationInside view of wireless wall switch Special Feature for Cold ClimatesLCD Liquid Crystal Display Hand-Held Remote Control Transmitter Operating InstructionsKey Settings IntroductionThermostat Function Manual FunctionCP Childproof Feature Continuous Pilot FeatureSetting LOCK-OUT CP Operational Notes Thermostatic Updating FeatureLocation of Vent Termination General VentingGeneral Venting Information Termination Location Canadian Installations1 US Installations2Application Quick Reference for Fresh Air Restrictor Plate / Flue BaffleDVT38N DVT38P DVT44N DVT44P Horizontal Termination Canadian InstallationsUSA Installations General Information Assembling Vent Pipes SK8 Venting PipesUse of the Restrictor Plates Horizontal Venting Applications Sidewall ApplicationsStep Sidewall InstallationVertical height requirement Always install horizontal venting on a level planeFresh Air Restrictor Plate Typical offset application Vertical Through-the-Roof InstallationMin 610mm Component Description Model Number Chimney ComponentsGlass Information Glass Frame Assembly RemovalGlass Cleaning Restrictor Plate InstallationAppliance Kit Model Description Ceramic Refractory InstallationDVT38IN Logs Log, Lava Rock and Ember PlacementPosition the Log Grate Burner. Remove the two DVT44IN LogsPosition the Log Rear Left Position the Log Front Left. Pos- FigurePosition the Log Front Middle Right DVT38IN logset complete Correct pilot flame appearance Flame CharacteristicsTrim Installation Lighting Instructions Lighting & Operating InstructionsTurning Off the Gas to the Appliance American Flame Gas Control System TroubleshootingIgniter operation Troubleshooting American Flame Gas Control System What to Check American Flame Gas Control System Error CodesConversion Procedure Conversion PrecautionsFuel Conversion Instructions Check Manifold Pressure Converting the Gas Control ValveValve Minimum Rate Screw Air Shutter SettingsPilot Flame Adjustment Injector Orifice Size MatrixCleaning the Control System MaintenanceBurner and Burner Compartment DVT38IN, DVT44IN Colonial Red Limestone Herringbone DVT38IN DVT44INFuel Conversion Kits Ceramic Refractory Kits AccessoriesBack-up Battery Kit Wall Mountable Wireless Remote TransmitterProduct Covered by this Warranty Limited Lifetime WarrantyModel EnerGuide Ratings Fireplace Efficiency % Efficiency Ratings