Lincoln Electric SVM103-C service manual Brush Removal and Replacement, Procedure

Page 71

Return to Section TOC

Return to Section TOC

Return to Master TOC

Return to Master TOC

F-23

TROUBLESHOOTING & REPAIR

F-23

 

 

 

 

 

BRUSH REMOVAL AND REPLACEMENT (continued)

FIGURE F.6 - BRUSHES RETAINED WITH CABLE TIE

CABLE

TIE

BRUSHES

Return to Section TOC

Return to Section TOC

Return to Master TOC

Return to Master TOC

PROCEDURE

1.Remove the spark plug wire.

2.Open the brush holder assembly cover. Squeeze the 2 tabs and depress the cover at the top with a screw driver or your fingernail. The cover will drop open on its bottom hinge.

3.With the 1/4” nut driver, remove the 2 screws that hold the brush holder assembly in place.

4.With the needle nose pliers, gently remove the black and the red wires.

Note: The red wire is inboard. “RED” is marked on the brush holder beside the terminal for the red wire.

5.To change the brushes, use the slot head screw driver to pop off the plastic retainer on the back of the brush holder assembly.

6.Remove the old brush assemblies and insert the new ones. One cor- ner of the terminal clip is beveled so that the brush can go in only one way.

7.Snap the plastic retainer back onto the brush holder. The brushes may need some repositioning; wiggle them slightly to help them seat properly on the slip rings.

POWER-ARC 4000

Image 71
Contents Safety Depends on You POWER-ARCCalifornia Proposition 65 Warnings SafetyElectric Shock can kill Welding Sparks can cause fire or explosion Précautions DE Sûreté Master Table of Contents for ALL Sections Table of Contents Installation Section Technical Specifications POWER-ARC InstallationStoring Safety PrecautionsLocation and Ventilation PRE-OPERATION Engine Service Cert. Kool Bore Spark Arrester125 amp Electrical Output ConnectionsWelding Cable Connections Cable Size forPlugs and HAND-HELD Equipment Auxiliary Power ReceptaclesMachine Grounding Circuit Breakers Premises WiringThese Devices Without POWER-ARC Table of Contents Operation Section General Description Safety InstructionsOperation Operating InstructionsWelding Capability Operational Features and ControlsDesign Features Advantages Recommended ApplicationsGENERATOR/WELDER Controls Controls and Settings20 AMP, 120 Volt Duplex Receptacle Gasoline Engine ControlsStarting the Engine Engine OperationBefore Starting the Engine For a HOT Engine General Information To USE the Generator AS AN Auxiliary Power SupplyGenerator Operation Suggested Power Applications Running Watts Start-up Watts Table B.1 Generator Power ApplicationsWelding Operation Table B.2 Welding APPLICATIONS/ELECTRODE Selection Guide Welding GuidelinesOperation What Happens in the Arc? Correct Welding Position Correct Arc Length Butt Welds PracticeUse the following Do the followingPenetration Fillet WeldsVertical-Down Welding Vertical-Up WeldingWelding Sheet Metal Overhead WeldingHardfacing To Reduce Wear Cast Iron Plate Preparation Welding Cast IronLow Hydrogen Group Stable-Arc E7018 High-Speed Group AWS E6013Out-of-Position Group AWS E6011 Table of Contents Accessories Section Lincoln Electric Accessories AccessoriesOPTIONS/ACCESSORIES Table of Contents Maintenance Section Engine Adjustments MaintenanceRoutine and Periodic Maintenance Engine MaintenanceFigure D.2 Clean Rotating SCREEN/FINGER GUARD/DEBRIS Guard Table D.1 Engine Maintenance Schedule Do not attempt to polish slip rings while engine is running GENERATOR/WELDER MaintenanceFigure D.6. Major Component Locations Table of Contents Theory of Operation Section ENGINE, EXCITATION, Rotor and Stator Theory of OperationFigure E.3 Field Excitation and Auxiliary Power Rotor Field Feedback and Auxiliary PowerWeld Winding and Reactor Auxiliary Power Overcurrent ProtectionTable of Contents Troubleshooting & Repair Section HOW to USE Troubleshooting Guide Troubleshooting & RepairOutput Problems TroubleshootingVice Facility Or contact your local LincolnElectric Authorized Field Ser Local Lincoln Electric Authorized Field Service FacilityTroubleshooting Rotor Resistance Test Engine Problems Troubleshooting Engine Throttle Adjustment Materials Needed This procedure takes approximately 15 minutes to performRotor Voltage Test Test DescriptionRotor Voltage Test Test ProcedureRotor Resistance Test This procedure takes approximately 25 minutes to performRotor Resistance Test Figure F.3 Brushes Retained with Cable TIE This procedure takes approximately 20 minutes to perform Engine Throttle Adjustment TestOscilloscope Method Strobe-tach MethodFrequency Counter Method Wing NUT High Speed Stop Screw High Idle no Load Scope SettingsNormal Open Circuit Weld Voltage Waveform Normal Open Circuit Voltage Waveform 115 VAC Supply Machine Loaded to 125 Amps AT 23 VAC Typical Weld Output WaveformMachine Loaded Description Brush Removal and ReplacementProcedure Brush Removal and ReplacementProcedure Rheostat Removal and Replacement Figure F.7 Rheostat Removal This procedure takes approximately 35 minutes to perform Capacitor AND/OR Diode Bridge Removal and ReplacementFigure F.8 Location and Discharging the Field Capacitor Procedure Capacitor Removal and REPLACE- MentFigure F.8A Field Diode Bridge Location Procedure Field Diode Bridge Removal and ReplacementInstructions STATOR/ROTOR Removal and ReplacementThis procedure takes approximately 3 hours to perform STATOR/ROTOR Removal and Replacement Troubleshooting & Repair Rotor Removal Procedure Figure F.12 Checking ROTOR-STATOR AIR GAP WELDER/GENERATOR OUTPUT1 Auxiliary Power Receptacle OUTPUT1Retest After Repair Engine OutputReturn to Section TOC Table of Contents Diagrams Section Wiring Diagram Power ARC DiagramsDIAGRAMSG-3 DIAGRAMSG-4 Dimension Print Power ARC Return to Section TOC SVM Error Reporting Form