D1.8 Seismic Supplement Welding Manual
17
For
Techniques
All tack welds made under D1.8 are required to be made with the preheat as listed in the WPS. Tack welding on members in the protected zone is restricted, generally being prohibited except when made in certain locations, such as within the joint. Specific provisions apply to the removal of improperly placed tack welds. See D1.8, clause 6.6 and 6.16.
Minimum lengths for weld tabs have been imposed by D1.8. Where practicable, weld tabs are to be at least the thickness of the part, but no less than 1 inch. However, they need not exceed 2 inches in length. Tack welds that attach weld tabs in the protected zone must be made within the joint. See D1.8, clause 6.10.
The sequence of depositing the half length weld beads associated with making Demand Critical welds in beam bottom
Contractors must establish and implement an identification system by which the welder welding on each joint can be identified. See D1.8, clause 6.13.
The protected zone is the region within the structural member in which plastic hinging is expected to occur during seismic events. In order to facilitate this inelastic deformation (instead of initiating fracture), the protected zone must be kept free of notches and gouges, as well as miscellaneous attachments that may impede the desired behavior of the member. With the exception of arc spot welds used to hold steel decking in place, unauthorized welds and attachments should not be made in the protected zone. This would include, but not be limited to, welded studs, erection aids, and attachments for
If unauthorized welds are inadvertently added to the protected zone, D1.8 provides techniques to be used when corrective measures are mandated. Magnetic particle inspection (MT) of these repaired regions is typically required. See D1.8, clause 6.15.
www.lincolnelectric.com