INSTALLATION CHECKS

Testing for backfeed. If a backfeed condition is indicated, disconnect from shorepower and disconnect the AC output wires from the inverter. Make sure the inverter is OFF.

Caution: Apply shorepower and measure for voltage between the black and white wires that were attached to the inverter output feeding the electrical panel or loads, not the inverter output wires. If there is voltage on these wires, a backfeed condition exists and must be corrected or damage will result.

3.Test the battery charger function:

With shorepower applied and the

transfer switch engaged, the battery charger should be in operation. The CHARGE LED will blink for 8 seconds. After the 8 seconds, the unit will enter the charge mode and the LED will be illuminated. (When using Temperature Sensitive Charging, this time may be longer.)

When AC is available, the unit will auto- matically default to charge mode without the operator setting the unit in CHARGE mode. It is necessary to press the CHARGE switch OFF, if you do not want to charge.

Verify the charger is working by using a volt meter. Use this same method on the start or auxiliary battery connected to the echo- charge to verify echo-charge operation. The battery voltage should gradually increase.

If using a Remote Control Panel, DC Amps LED indicates charger output and the DC Volts LED indicates an increase in battery voltage.

Note: The house battery bank must be above 13.0 volts for the echo-charge to be operational.

Turn the inverter ON—the green LED should blink. Remove shorepower and the inverter should automatically pick up the AC load when shorepower is removed.

Repeat the test for transfer and battery charger with the generator if you have one.

Congratulations, you have completed a successful installation.

Note: For low power system shutdown mode, both the INVERT and CHARGE LEDs must be OFF.

38

Image 38
Contents Page Safety Summary DisclaimerTable of Contents Freedom Watts Freedom Amps DCIntroduction Inverter Idle Circuit Power SharingCircuit Breaker Protection Temperature Sensitive Charging TSC Electronic ProtectionOperation Invert ModeCharge Mode Battery Type Selection LOW Battery Red LEDLOW Battery & OVER-TEMP/OVERLOAD OVER-TEMP/OVERLOAD Red LEDTSC Temperature Sensitive Charging Optional RemotesAdvanced Remote Control Panels Link Instruments Optional Remote Control PanelsRemote Control Panel LinkBattery Types Wet Cell BatteriesBattery Interconnection BatteriesParallel Parallel ConfigurationBattery Bank Ratings and Sizing AMP-HOUR Consumption Formulas Freedom Battery Chargers Battery ChargingBattery Charging Battery charger stages are Acceptance to Float Transition Points Battery Charging Battery Charger Voltage Settings Confirm that your shipping carton contains Installation PrecautionsAccessories Needed for Installation Typical Tools NeededInstallation Key Installation Points+ Positive Negative Grounding Neutral BondingWhite to White AC WiringGround/green Black to BlackDC Wiring InstallationGround Fault Circult Interrupters Battery Cable Connections Battery Cable Fusing For Freedom 10Inverter/charger configurations Installation OptionsInstallation Options Dual In/Dual Out Configuration Freedom Marine Installation Option Installation Option 1 for Freedom Marine 10, 15, 20, 25,Installation Option 2 for Freedom Marine 10, 15, 20, 25, Freedom Marine Model 10, 15, 20, 25Installation Option 3 for Freedom Marine 25 Freedom Marine Installation Option Installation Option 4 for Freedom Marine 25 Dual Input/ Dual Output Installation Checks Test the transfer functionTest the battery charger function Troubleshooting LED Status Troubleshooting VoltageGlossary LED Light Emitting Diode Indicator light Specifications Warranty What does this warranty cover?Product Return Procedure Page Xantrex Technology Inc