9. Maintenance
MA6
MA7
MA8
MA9
This machine is equipped with a spring loaded
Apply following procedures if readjustment is required:
(1)Cutting head
(2)Spring
(3)Drive case
1.Slacken 3 pieces of flange nuts which are holding the cutting head. (MA7)
(1) Slacken
2. Slacken a bracket bolt on the starter side. (MA8)
(1) Slacken
3.By up and down the cutting head several times, belt tension is regulated automatically by a spring force.
4.Tighten those slacken bolt and nuts as original.
■BELT EXCHANGE
As the belt wears out, correct tension cannot be maintained just by its adjustment. In such a case, ask your sales dealer to exchange, or purchase new belt and exchange in following procedure:
IMPORTANT
The belt for exchange shall be a genuine part (Part No.
DISASSEMBLING PROCEDURE
1.Slacken 2 screws and remove a pulley cover.
2.By plug wrench, slacken 3 nuts which are holding the cutting head. (MA9)
(1) Cutting head (2) Pulley cover
23