Cisco Systems ASR 1004 quick start Remove and Then Replace a DC Power Supply

Page 31

Note Two power supplies must be installed in the chassis at all times to ensure sufficient cooling. The system fans are inside the power supply units and must spin for cooling. Because all the system fans can be powered by one power supply, the second power supply unit does not have to be powered on, but it must be installed.

Caution If you remove a power supply, the system can run for a maximum of five minutes before the system shuts down. The fans and power elements are independent within the power supply. Therefore, it is not required that the replacement power supply be energized within five minutes. The only requirement is that the power supply be installed in the chassis, which energizes the fans and maintains proper system cooling.

Step 6 Grasping the power supply handles, pull the power supply from the chassis.

Step 7 Replace the AC power supply within five minutes or the system will shutdown.

You have removed an AC power supply from the Cisco ASR 1004 Router and now must replace the AC power supply within five minutes. Follow these steps:

Step 1 Insert another AC power supply in power supply Slot 0 or power supply Slot 1 until it is full seated.

Step 2 Tighten the captive screws. Insert the AC power cable.

Step 3 Plug the power supply cable into the power source.

Step 4 Place the power supply Standby switch in the On (I) position.

Step 5 The power supply LEDs light when power is supplied to the router.

You have completed a live change-out procedure (that is, removing and replacing an AC power supply) for an AC power supply not operating properly in the Cisco ASR 1004 Router within five minutes

Remove and Then Replace a DC Power Supply

Because of the power supply redundancy, there is no need to power off the Cisco ASR 1004 Router before removing one of the DC power supplies.

Warning

Before performing any of the following procedures, ensure that power is removed from the DC circuit. Statement

 

 

1003

 

 

 

 

 

 

Warning

Only trained and qualified personnel should be allowed to install, replace, or service this equipment.

 

 

Statement 1030

 

 

 

 

 

Warning

Installation of the equipment must comply with local and national electrical codes. Statement 1074

 

 

 

Step 1 Before servicing the power supply, switch the circuit breaker Off in your equipment area. Step 2 Slip on the ESD-preventative wrist strap that was included in the accessory kit.

Step 3 Switch the power supply circuit breaker switch to Off (O).

Step 4 Locate the terminal block on the rear of the chassis on the power supply.

Step 5 Remove the terminal block plastic cover and then follow these steps:

a.Unscrew the negative cable Kepnut screw, washer, and ground lug, and remove the stud and lead wire.

31

Image 31
Contents Cisco ASR 1004 Router Document Revision History Documentation and ResourcesTools and Parts Prepare for InstallationPrepare for Equipment Shelf or Tabletop Installation Site Preparation and UnpackingRack-Mount the Router Prepare for Rack-Mount InstallationAttach the Rack-Mount Brackets-Chassis Front-Mounted Attach the Rack-Mount Brackets-Chassis Rear-Mounted Installing the Cisco ASR 1004 Router in a Four-Post Rack Four-Post Rack InstallationPage Installing a Cisco ASR 1004 Router in a Two-Post Rack Two-Post Rack InstallationAttach the Cable-Management Bracket Chassis Ground Connection Installation Chassis ground connector on the Cisco ASR 1004 Router Console and Auxiliary Port Cable Connections Connect the Router to the NetworkManagement Ethernet Port Cable Connection Cisco ASR1000-RP1 Enet Management Port ConnectorConnect the Shared Port Adapter Cables Install Cables in the Cable-Management BracketConnect AC Power to the Router Start the SystemCisco ASR 1004 Router AC Power Supply Connect DC Power to the RouterUnit. Statement Installing the DC Ground Lugs Wiring the DC-Input Power Source Cisco ASR 1004 Router DC Power Supply Terminal Block Start the Cisco ASR 1004 Router Verifying Power Supply OperationLED Page Page Using the Console Interface Configure the RouterConfigure Global Parameters Using the Setup Facility OK? No clns routing Tftptimeout Page Save the Running Configuration to Nvram Check the Running Configuration SettingsPerform Other Configuration Tasks Power Off the Cisco ASR 1004 Router After InstallationRemove and Replace a Power Supply Remove and Then Replace a DC Power Supply Page End View All measurements in inches 267 Holes Install and Remove the SPA Interface Processor SIP ASR1000-SIP10 Remove the Shared Port AdapterPage USA