Relay/Transformer (R/T Box)

Standard Transition

Each MX250 microprocessor based ATS controller requires a relay/transformer box to apply line voltage to the ATS operator via coil control relays. Also required is power for the MX150 printed circuit board and an appli- cation of sensing voltage proportional to line voltage. This is accomplished by the relay transformer box. This method of switching operator voltage and applying power and sensing voltage to the printed circuit board isolates

1

2

(inside)

3

Figure 12

40-225 Amp Molded Power Section

Transformer Usage (see Figure 12)

R/T Box

Primary

1 VA

25 VA

Assembly

Voltage

XFMR

XFMR

Part No.

at 50/60 Hz

Part No.

Part No.

 

 

 

 

57P-1015

120V

K-3216

K-3224

57P-1016

208-220V

K-3217

K-3225

57P-1017

230-240V

K-3218

K-3226

57P-1018

277V

K-3219

K-3227

57P-1019

380-400V

K-3220

K-3228

57P-1020

416-440V

K-3221

K-3229

57P-1021

460-480V

K-3222

K-3230

57P-1022

575-600V

K-3223

K-3231

 

 

 

 

Bill of Material

Item

Part No.

Description

Qty

 

 

 

 

1

See Chart

Transformer (1 VA)

2

2

See Chart

Transformer (25 VA)

2

3

K-1274

Relay Flange Mounted

2

 

 

 

 

the MX250 from the line voltage, further protecting

the controller from harmful line transients. Two versions of the R/T box exist depending on the type of ATS (standard transition or delayed transition).

The following layout drawings of the R/T Box compo- nents (standard and delayed transition) include a bill of materials for replacement parts. Schematics are included to indicate proper wiring.

PRI.

PRI.

PRI.

 

SEC.

 

1

SEC.

SEC.

 

2

3

Figure 13

40-3000 Amp - All Other Standard Types

Transformer Usage (see Figure 13)

R/T Box

Primary

1 VA

25 VA

Assembly

Voltage

XFMR

XFMR

Part No.

at 50/60 Hz

Part No.

Part No.

 

 

 

 

50P-1026

120V

K-3216

K-3224

50P-1027

208-220V

K-3217

K-3225

50P-1028

230-240V

K-3218

K-3226

50P-1029

277V

K-3219

K-3227

50P-1030

380-400V

K-3220

K-3228

50P-1031

416-440V

K-3221

K-3229

50P-1032

460-480V

K-3222

K-3230

50P-1033

575-600V

K-3223

K-3231

 

 

 

 

Bill of Material

Item

Part No.

Description

Qty

 

 

 

 

1

See Chart

Transformer (25 VA)

2

2

See Chart

Transformer (1 VA)

2

3

K-1260

Coil Control Relay (24V)

2

 

 

 

 

26

Entelli-Switch 250 Operation and Maintenance Manual (71R-2000)

GE Zenith Controls

Image 26
Contents GE Zenith Controls Introduction Authorized ServiceTable of Contents Final Equipment Inspection Safety / InstallationEquipment Inspection and Storage Initial Energization Installation cont’dEngine Start Control Connections Initial Energization cont’d R E T E S TInstallation cont’d Entelli-Switch 250 Controller Entelli-Switch 250 ControllerEntelli-Switch 250 Controller cont’d LCD & KeypadUser Setting for Voltage & Frequency Accessory Group Packages Stds Exes Cons Sens Spes PsgsCalibrate Accessory DefinitionsA62 Accessory Definitions cont’d S13P Approximate out of phase degreesS12P S14How to Set the System Clock Press More and scroll to SET System Clock using the More keyPress Bypass Exer CDT One Event Timer ExerciserPress Exer Cancl Press Start Timer Test Press Cancl BpassCDP Clock Exerciser Load / No-Load Clock ExerciserEntelli-Switch 250 User Setup CFG Menu Turn options on or OFF via keypad through the CFG menuEntelli-Switch 250 User Setup SET Menu Change adjustable values through the SET menuEntelli-Switch 250 User Setup System Info View System DataTest Options TestingIntroduction Auto PositionDelayed Transition Testing cont’dATS Testing Standard TransitionRe-Transfer with Closed Transition Closed TransitionInitiating a Closed Transition Test Location Emergency Service Procedure for Extended Parallel TimeAuto Location Sequence of Operation ATS TypeSequence of Operation cont’d Amp Molded Power Section Transformer Usage see Figure Relay/Transformer R/T BoxDelayed / Closed Transition Relay/Transformer R/T Box cont’dStandard Transition R/T Box Schematic Delayed / Closed Transition R/T Box SchematicTroubleshooting and Diagnostics General TroubleshootingTesting Maintenance and TestingInspection and Cleaning ServicingPage GE Zenith Controls