GE Entelli-Switch 250 manual Maintenance and Testing, Inspection and Cleaning, Servicing

Page 30

Maintenance and Testing

CAUTION

Due to hazardous voltage and current, GE Zenith rec- ommends that a GE Zenith Certified technician or a qualified electrician must perform the

installation and maintenance of the switch.

CDT battery replacement - lithium batteries may last up to 10 years, however it is recommended that battery replacement be included in a 3-5 year service cycle. The battery maintains the exerceser memory only and does not otherwise affect the operation.

WARNING

Both power sources must be disconnected before manual operation of the switch.

A preventive maintenance program will insure high reliability and long life for the transfer switch. The preventive maintenance program for the transfer switch should include the following items:

Inspection and Cleaning

The switch should be inspected for any accumulation of dust, dirt, or moisture, and should be cleaned by vacuuming or wiping with a dry cloth or soft brush. do not use a blower since debris may become lodged in the electrical and mechanical components and cause damage.

Remove the transfer switch barriers and check the condition of the contacts. Any surface deposits must be removed with a clean cloth (do not use emery cloth or a file). If the contacts are pitted or worn excessively, they should be replaced. A general inspection of mechanical integrity should be made to include loose, broken or badly worn parts.

Servicing

All worn or inoperative parts must be replaced using GE Zenith recommended replacement parts. Please refer to the Replacement Parts manual for specific part information and ordering procedures. Please contact the GE Zenith Technical Services Department for the Replacement Parts manual.

The operating mechanism of the transfer switch is lubricated with Lubriplate 105. The lubricant applied at the factory provides adequate lubrication for the lifetime of the switch. Should debris contaminate the mechanism, clean and apply additional Lubriplate.

GE Zenith can provide complete preventative main- tenance services. Please contact the GE Zenith Technical Services Department for additional information.

Testing

A manual operator handle is provided with the transfer switch for maintenance purposes only. Manual operation of the switch must be checked before it is operated electrically. Both power sources

must be disconnected before manual operation

of the switch. Insert the handle and operate the transfer switch between the Source 1 and Source 2 positions. The transfer switch should operate smoothly without binding. Return the switch to Source 1 position, remove the handle, and return it to

the holder provided.

After completing the inspection, cleaning and servicing of the transfer switch, reinstall the switch cover, and close and lock the cabinet door. Reclose the circuit breakers feeding the utility and generator sources to the switch.

Initiate the electrical transfer test by activating the TS test switch. P timer will time out and the micro- controller will send an engine start signal. When the W time has elapsed, the switch will complete its transfer by closing into Source 2.

Deactivating the test switch will start retransfer to Source 1. The switch will complete its retransfer to Source 1 after the time delay of the T timer.

The U engine overrun timer allows the engine generator to run unloaded for a preset cool down period.

NOTE: A periodic test of the transfer switch under load conditions is recommended to insure proper operation. (See National Electric Code articles 700 and 701).

WARNING

When performing a hi-pot or dielectric test on the power section, DISCONNECT the control panel plugs from the microprocessor to avoid potential damage.

30

Entelli-Switch 250 Operation and Maintenance Manual (71R-2000)

GE Zenith Controls

Image 30
Contents GE Zenith Controls Authorized Service Table of ContentsIntroduction Safety / Installation Equipment Inspection and StorageFinal Equipment Inspection Installation cont’d Engine Start Control ConnectionsInitial Energization Initial Energization cont’d R E T E S TInstallation cont’d Entelli-Switch 250 Controller Entelli-Switch 250 ControllerEntelli-Switch 250 Controller cont’d LCD & KeypadUser Setting for Voltage & Frequency Accessory Group Packages Stds Exes Cons Sens Spes PsgsAccessory Definitions A62Calibrate Accessory Definitions cont’d S13P Approximate out of phase degreesS12P S14How to Set the System Clock Press More and scroll to SET System Clock using the More keyPress Bypass Exer CDT One Event Timer ExerciserPress Exer Cancl Press Start Timer Test Press Cancl BpassCDP Clock Exerciser Load / No-Load Clock ExerciserEntelli-Switch 250 User Setup CFG Menu Turn options on or OFF via keypad through the CFG menuEntelli-Switch 250 User Setup SET Menu Change adjustable values through the SET menuEntelli-Switch 250 User Setup System Info View System DataTest Options TestingIntroduction Auto PositionDelayed Transition Testing cont’dATS Testing Standard TransitionClosed Transition Initiating a Closed TransitionRe-Transfer with Closed Transition Emergency Service Procedure for Extended Parallel Time Auto LocationTest Location Sequence of Operation ATS TypeSequence of Operation cont’d Amp Molded Power Section Transformer Usage see Figure Relay/Transformer R/T BoxDelayed / Closed Transition Relay/Transformer R/T Box cont’dStandard Transition R/T Box Schematic Delayed / Closed Transition R/T Box SchematicTroubleshooting and Diagnostics General TroubleshootingTesting Maintenance and TestingInspection and Cleaning ServicingPage GE Zenith Controls