HP E5500-48-POE Planning IRF fabric setup, Planning IRF fabric size and the installation site

Page 59

Step

 

 

 

Description

 

 

 

 

 

Plan the installation site and IRF fabric setup parameters:

 

 

 

 

 

Planning IRF fabric size and the installation site

1.

Plan IRF fabric setup

 

Identifying the master switch and planning IRF member IDs

 

Planning IRF topology and connections

 

 

 

 

 

 

 

 

 

 

Identifying physical IRF ports on the member switches

 

 

 

 

 

Planning the cabling scheme

 

 

 

 

 

2.

Install

IRF

member

See “Installing the switch.”

 

switches

 

 

 

 

 

 

 

 

 

 

 

 

 

3.

Connect

the

grounding

See “Grounding the switch” and “Connecting the power cord.”

 

cable and power cords

 

 

 

 

 

 

4.

Power on the switches

 

N/A

 

 

 

 

 

 

5.

Install interface cards

 

This step is required only for the 5120 EI switches.

 

See “Installing/removing an interface card (only for the 5120 EI switches).”

 

 

 

 

 

 

 

 

 

 

 

6.

Configure

 

basic

IRF

See “Configuring basic IRF settings.”

 

settings

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7.

Connect the physical IRF

See “Connecting the physical IRF ports.”

All switches except the master switch automatically reboot, and the IRF fabric

 

ports

 

 

 

 

 

 

 

 

is established.

Planning IRF fabric setup

Planning IRF fabric size and the installation site

Choose switch models and identify the number of required IRF member switches, depending on the user density and upstream bandwidth requirements. The switching capacity of an IRF fabric equals the total switching capacities of all member switches.

NOTE:

As your business grows, you can plug a switch into an IRF fabric to increase the switching capacity without any topology change or replacement.

Identifying the master switch and planning IRF member IDs

Determine which switch you want to use as the master for managing all member switches in the IRF fabric. An IRF fabric has only one master switch. You configure and manage all member switches in the IRF fabric at the command line interface of the master switch.

NOTE:

IRF member switches will automatically elect a master. You can affect the election result by assigning a high member priority to the intended master switch. For more information about master election, see the IRF configuration guide for your switch.

Prepare an IRF member ID assignment scheme. An IRF fabric uses member IDs to uniquely identify and manage its members, and you must assign each IRF member switch a unique member ID.

54

Image 59
Contents HP 5120 EI & 5120 SI Switch Series Page Contents Page Iii Type Product code HP description Alias Models in the HP 5120 EI Switch SeriesModels in the HP 5120 SI Switch Series Product overview5120-24G EI 2 slots/5120-24G EI TAA 2 slots panel views Regulatory Model Numbers in the HP 5120 8G SI Switch Series5120-48G EI 2 slots/5120-48G EI TAA 2 slots panel views 5120-24G EI panel views 5120-48G EI panel views 5120-48G EI switch does not support interface cardsFront panel Front panel 5120-16G SI panel views 5120-8G SI panel views5120-48G SI panel views 5120-24G SI panel views5120-8G-PoE+ SI panel views 5120-8G-PPoE+ SI panel views5120-24G-PPoE+ SI panel views 5120-24G-PoE+ SI panel views Temperature/humidity Preparing for installationSafety recommendations Examining the installation siteHarmful gas limits in the equipment room CleannessLaser safety Dust concentration limit in the equipment roomInstallation tools Hardware installation flow Installing the switchMounting brackets Installing a 5120 EI switch in a 19-inch rackInstallation methods Chassis Front mounting brackets Rear mounting brackets Rack-mounting by using only front mounting bracketsMounting bracket kit shipped with the 5120 EI switches Attach the front mounting brackets to the chassis Attach the front mounting brackets to the rack Rack-mounting by using front and rear mounting brackets Attach the rear mounting brackets to a rack Mount the switch in the rack Attach the front brackets to the rack Installing a 5120 SI switch in a 19-inch rackChassis Bracket view Mounting position Attaching the mounting brackets to the switch chassisTo attach the mounting brackets to the switch chassis Front mounting position 5120-16G SI/5120-24G SI Front mounting position 5120-8G-PoE+ SI/5120-8G-PPoE+ SI Rack-mounting the switch Mount the switch in a rack 5120-16G SI Mounting the switch to a wall Mounting the switch on a workbenchModel Hole distance Installation procedureIntroduction to wall anchor kit Models supporting wall mountingIntroduction to magnetic mounting kit Mounting the switch through magnet mountingMagnet mounting kit Grounding the switch with a grounding strip Grounding the switchPage Make a grounding cable connector Ground through the PE wire of the AC power cord Grounding the switch by using the AC power cordConnecting the AC power cord Connecting the power cordConnect the AC power cord to the 5120-48G EI switch Connecting the switch to a +12 VDC output RPSConnect the RPS cable to the -52 to -55 RPS receptacle Connecting the switch to a -52 to -55 VDC output RPSRemove the filler panel over an interface card slot Installing an interface cardRemoving an interface card Installing/removing a dedicated CX4/SFP+ cableRemoving a dedicated CX4/SFP+ cable Verifying the installationConnection procedure Accessing the switch for the first timeSetting up the configuration environment Connecting the console cableConnection description Setting terminal parametersSet the serial port parameters Set the serial port used by the HyperTerminal connectionHyperTerminal window Powering on the switch Powering on the switchVerification before power-on Description Boot menu optionsEnter Y at the prompt Changing the startup modeEnter 9 to change the startup mode Finished User interface aux0 is available Press Enter to get started To set up an IRF fabric Setting up an IRF fabricIRF fabric setup flowchart Step Description Planning IRF fabric setupPlanning IRF fabric size and the installation site Identifying the master switch and planning IRF member IDs5120 EI IRF fabric in daisy chain topology Planning IRF topology and connections5120 SI IRF fabric in daisy chain topology Identifying physical IRF ports on the member switchesPhysical IRF port requirements Switch chassis Candidate physical Requirements IRF portsPlanning the cabling scheme Page Shows the IRF fabric topology Configuring basic IRF settingsTo do … Use the command… Connecting the physical IRF portsAccessing the IRF fabric to verify the configuration Display and maintain IRF configuration and running statusConsole login password loss Maintenance and troubleshootingPassword loss Power supply failureAC input Mark State Fan failure only for the 5120 EI switchesConfiguration terminal problems LED behaviors that identify a fan failureChassis Dimensions H × W × D Weight Appendix a Technical specificationsPhysical specifications Chassis dimensions and weightsChassis Operating temperature Relative humidity Environmental specificationsPower specifications Power input typesPower consumption specifications for non-PoE switches AC input voltage specificationsRPS DC input voltage specifications and RPS compatibility Cooling system Power consumption specifications for PoE switchesChassis Fixed fans Appendix B FRUs and compatibility matrixes Interface cards only for the 5120 EI switchesGE SFP+ transceiver modules GE SFP transceiver modulesProduct code Cable description Cable length SFP+ cablesCX4 cables Product code Cable description Connector type Cable lengthGE XFP transceiver modules UTP/STP Page 10/100/1000Base-T Ethernet port Appendix C Ports and LEDsPorts Console portSystem status LED LEDs for the 5120 EI switchesCombo interface only available on the 5120 EI switches Seven-segment LED Port mode LEDRPS status LED Seven-segment LED description SFP port LED Port mode LED Mode Port LED status Description Status10/100/1000Base-T Ethernet port LED Interface card status LED LEDs for the 5120 SI switchesPower LED Status Description RPS status LED descriptionEthernet port LED description 5120-48G SI Ethernet port LEDs description 5120-16G SI/5120-24G SI Port mode LED Mode Port LED1000Base-X SFP port LEDs description 1000Base-X SFP port LEDRelated information Support and other resourcesContacting HP Convention Description ConventionsConvention Description Network topology icons Index Verifying the installation,43