To Set Up the Interface Pod
To Set Up the Interface Pod
Caution | Handle the interface pod with care to avoid electrostatic discharge (ESD) | |
| damage during unpacking, installation, and operation. The connectors on | |
| the front and rear of the interface pod are susceptible to ESD. | |
| 1 | Insert the interface pod into the analyzer. |
|
| See “To Insert the Interface Pod” on page 7. The procedure is the same for |
|
| all interface pods. |
| 2 | Connect the interface pod to the system under test. |
|
| See “To Connect to the System Under Test” on page 8. The analyzer |
|
| automatically recognizes and configures the interface pod. |
| 3 | If you want to change any of the configuration parameters, see “To |
|
| Manually Configure the Interface Pod” on page 11. |
6