CLEARANCE ON ALL SIDES

MINIMUM CLEARANCE

ABOVE UNIT

6 (152)

12 (305)

36 (914)

ACCESS PANEL

NOTES:

SClearance to one of the other three

30 (762)

 

sides must be 36 inches (914mm).

 

 

 

 

SClearance to one of the remaining

two sides may be 12 inches (305mm) and the final side may be 6 inches (152mm).

LINE SET

CONNECTIONS

48 (1219)

MINIMUM CLEARANCE BETWEEN

 

TWO UNITS

 

 

ACCESS PANEL

24 (610)

LINE SET

 

 

CONNECTIONS

Figure 4. Installation Clearances

DETAIL A

INSTALL UNIT AWAY

FROM WINDOWS

DETAIL B

Install unit level or, if on a slope, maintain slope tolerance of 2 degrees (or 2 inches per 5 feet [50 mm per 1.5 m]) away from building structure.

DISCHARGE AIR

BUILDING

STRUCTURE

TWO 90_ ELBOWS INSTALLED IN LINE SET

WILL REDUCE LINE SET VIBRATION

MOUNTING

SLAB

GROUND LEVEL

Figure 5. Placement, and Slab Mounting

New Unit Placement

See Unit Dimensions on page 2 for sizing mounting slab, platforms or supports. Refer to figure 4 for mandatory installation clearance requirements.

POSITIONING CONSIDERATIONS

CAUTION

In order to avoid injury, take proper precaution when lifting heavy objects.

Consider the following when positioning the unit:

SSome localities are adopting sound ordinances based on the unit’s sound level registered from the adjacent property, not from the installation property. Install the unit as far as possible from the property line.

SWhen possible, do not install the unit directly outside a window. Glass has a very high level of sound transmission. For proper placement of unit in relation to a window see the provided illustration in figure 5, detail A.

Page 7

14ACX SERIES

Image 7
Contents Condensing Units Table of ContentsShipping and Packing List GeneralSide View Unit Dimensions − Inches mmModel Number Identification AC X −024 − 230 −13 Typical Unit Parts ArrangementTorque Requirements Operating Manifold Gauge Set and Service ValvesUsing Manifold Gauge SET Operating Service Valves11 12 98 7 6 2CONNECT Manifold Gauge SET Recovering Refrigerant from Existing System1DISCONNECT Power Recovering RefrigerantPositioning Considerations New Unit PlacementClearance on ALL Sides Minimum Clearance Above Unit Minimum Clearance Between TWO UnitsStep Removing and Installing LouversPlacing Unit on Slab Roof MountingMineral oils are not compatible with HFC−410A. If oil New or Replacement Line SetRefrigerant Line SET From Vertical to Horizontal InstallationRefrigerant Line SET Alling Vertical Runs NEW Construction ShownBrazing Connections 1CUT and Debur Brazing Procedures7PREPARATION for Next Step Wrap Service ValvesFlow Nitrogen 6BRAZE Line SETFlushing Line Set and Indoor Coil 2CONNECT Gauges and Equipment for Flushing ProcedureEqualizer Line Installation Installing Indoor Metering DeviceIndoor Expansion Valve Installation Sensing Bulb InstallationLeak detector must be capable of sensing HFC refrigerant Leak Test Line Set and Indoor CoilConnect Gauge SET Evacuating Line Set and Indoor Coil24VAC Transformer ElectricalLOW Voltage Control Wiring Single Phase High Voltage / Ground WiresTypical Factory Wiring Diagram Copeland Compressor Typical Factory Wiring Diagram Interlink Compressor System Refrigerant Connections for Testing and ChargingServicing Units Delivered Void of Charge Unit Start−UpStart Determine how refrigerant is metered Checking AIR Flow AT Indoor CoilBelow Calculating System Charge for Outdoor Unit Void of ChargeHFC−410A Subcooling TXV Charge Superheat RFC Start Measure outdoor ambient temperatureProblem exists with some component in the system System Operation MaintenanceUnit Components Homeowner Start−Up and Performance Checklist