Raypak 2600401 Heat Exchanger Removal, Heat Exchanger Re-assembly, Combustion Chamber Removal

Page 29

The heater may be cleaned from the side opposite the water connections, without breaking pipe connections. It is preferable, however, to remove both headers for better visibility through the tubes and to be sure the residue does not get into the system. Generally, you do not remove the top pan or the heat exchanger .

After reaming with the auger, mount the wire brush and clean out the debris remaining in the tubes. Another method is to remove the heat exchanger, ream tubes and immerse heat exchanger in non-inhib- ited de-scale solvent.

Heat Exchanger Removal

1.Shut water, gas and electricity off, close valves and relieve pressure, remove relief valve. Remove side inspection panels.

2.Remove top holding screws.

3.Remove draft diverter, lift and remove top and flue collector on stack type models. Remove inspec- tion panels.

4.Loosen bolts and disconnect flange nuts on inlet- outlet header, loosen union(s) at gas pipe, and slide heater away from piping until studs clear the heater.

5.Remove heat exchanger corner brackets.

6.Remove combustion chamber clips at the four cor- ners of the heat exchanger.

7.Lift heat exchanger straight up using caution not to damage refractory.

Heat Exchanger Re-assembly

1.Heat exchanger water header O-rings should be replaced with new ones.

2.Install inlet-outlet and return water headers and install header retainer nuts and torque nuts even- ly.

3.Install the four (4) corner clips between tube sheets and refractory. Replace "V" baffles.

4.Install thermostat sensing bulbs in header wells and replace bulb retaining clips.

5.Install inlet and return pipes in water headers using pipe thread sealant.

6.Install water pressure relief valve, flow switch, and low water cutoff devices if so equipped.

7.Open water supply and return shut-off valves. Fill heater and water piping system with water. Check heater and piping system for leaks at full line pres- sure. Run system circulating pump for a minimum of 1/2 hour with heater shut-off.

8.Shut down entire system and vent all radiation units and high points in system piping. Check all strainers for debris. Expansion tank water level

should be at the 1/4 mark and the balance of the tank filled with air.

9.Install flue collector, jacket top and inspection pan- els. Install top holding screws. Install draft diverter and vent piping if so equipped.

10.If gas piping was disconnected, reconnect gas pip- ing system and check for leakage using a soap solution.

11.Check for correct water pressure and water level in the system. Make sure that system pump oper- ates immediately on the call for heat. The system is ready for operation.

12.Within two (2) days of start-up, recheck all air vents and expansion tank levels.

Combustion Chamber Removal

To remove combustion chamber you must first have removed the heat exchanger. Unbolt metal combus- tion chamber retainer from top and remove combustion chamber panels individually.

Fig. 33: Refractory Panels—Top View

29

Image 29
Contents Econopak Water Heaters Page Contents Are important but not related to personal injury hazards Temperature Time to Produce Serious Burn General SafetyTime/Temperature Relationships in Scalds Receiving Equipment General SpecificationsTank Code Requirements InstallationMounting Base ClearancesOutdoor Models Venting ConnectionsModels Model No Sq. in. of Each Free AreaModels 0260 Indoor ModelsVent Terminal/Indoor Stack Installation Vent Max Model No Connector Horizontal Diameter Length ftVent Pipe Draft Hood Heater Common VentsModel No Nat Pro Gas Supply ConnectionsSetting Gas Pressure Specifications Type Inches WC Regulator MinWater Connections & System Piping Gas Pressure Regulator0261 Low NOx WH1 with Pressure Relief Valve Relief ValveElectrical Wiring Standing Pilot Model Wiring DiagramsIntermittent Ignition Device IID Model Intermittent Ignition Device IID Models 0330 Intermittent Ignition Device IID Model 0261 Low NOx Intermittent Ignition Device IID Models 0331 & 0401 Low NOx Sequence of Operation Servicing ProceduresStart-up Procedures Honeywellpilot Robertshaw Pilot For Robertshaw Gas Valve Turn gas control System Shut Down ProcedureFor Automatic Ignition Models To Turn Off Gas To Appliance Testing the Ignition Safety Shut-offControls Inspection ProceduresLow NOx Heaters-Models BurnersHigh/Low Gas Pressure Switch Burner AdjustmentOperation Visual InspectionRepair Section Combustion Chamber Removal Heat Exchanger Re-assemblyHeat Exchanger Removal Causes TroubleshootingPiping Intermittent Pilot System- Honeywell S8600 Electrical Electronic Ignition IIDElectrical Standing Pilot Adjustments & Replacement of Components Control Well Replacement Circulator ReplacementTube Replacement Procedure Procedure for Cleaning Flue Gas Passage WaysLimitedpartswarrantyeconopakwaterheaters Page Page