COMPLETING THE INSTALLATION
Checking and Testing Operations
To complete the installation, perform the following checks and tests to ensure that the air conditioner is operating correctly.
1Review all the following elements in the installation:
◆Installation site strength
◆Piping connection tightness to detect any gas leakages
◆Connection wiring
◆
◆Drainage
◆Earthing wire connection
◆Correct operations (follow the steps below)
2Press the On/Off button.
Result: ◆ The indicator lights on the indoor unit flash at
◆ While the indoor unit opens, the indoor unit fan runs to start.
3Press the button.
Result: The outdoor unit operates in cooling mode as following the room temperature.
4 | Air flow direction | Press the |
| button and check that the air |
|
| flow blades work properly. | ||
|
|
|
|
|