Glass replacement

CAUTION

Always use gloves when handling

 

 

broken glass.

 

 

1.Put on gloves. Remove door from hinges by lifting the door up. Figure 48

2.Remove the 7/8" rope from around glass frame. Figure 49

3.Using a 5/16" socket, remove hex nuts from glass retain- ing brackets. Remove retaining brackets. Figure 49

4.Carefully remove broken glass.

5.Wrap new glass pane(s) with 3/4" gasket. Make sure you have 1/4" overlap on each side.

6.Place new glass in frame. For three-piece glass style frame, slide new glass into the 45° aluminum post (not shown).

7.Fasten retaining brackets back into place with 5/16" nuts.

8.Replace 7/8" rope. Make sure the joint is at the bottom and there is no gap.

9.Slide door back down the hinges. Figure 48

Preformed

Glass

ST1117

Gasket

Retaining

Bracket

Figure 49 -

Replace Formed Glass

WARNING

Make sure the glass panel edges do not

touch any metal parts during thermal

 

 

expansion.

 

 

 

Door

Hinges

Figure 48 -

Remove Door from Hinges

ST1116

Retaining

Brackets

Hex Nuts

(not all shown)

Rope

Gasket

NOTE: Use only original MHSC replacement parts.

32

46D0232

Image 32
Contents Stratford What to do if YOU Smell GASTable of Contents SS38 Direct Vent Gas StoveOwner Important Safety InformationInstaller Listed Vented GAS Stove Heater Important Safety InformationCode Approval Product features Product SpecificationsInstalling Above 2000 Feet Gas Specifications & Orifice SizeSS38 Direct Vent Gas Stove General Installation Information Stove LocationClearances to combustibles Front of the heaterInstructions exactly can create a fire hazard Full width and depth of the applianceVenting Installation Information Installation PrecautionsInstallation Planning For Horizontal TerminationInstalling a vent system in an Outside chase Venting Installation InformationCanadian Installations1 US Installations2 47.5 121cm Venting installation Installation for Horizontal TERMI- NationDo not recess vent terminal into a wall or SidingVenting Installation Horizontal termination configurations Horizontal Venting Vertical V Minimum Horizontal H MaximumInstallation for Vertical TERMINA- Tion Venting InstallationVenting Installation Flat Ceiling Installation Cathedral Ceiling InstallationVertical Termination CONFIGURA- Tions Horizontal H + H1 Minimum Vertical Venting with Two 2 Elbows Horizontal H + H1Vertical Venting with Two 2 Elbows Check gas type Install gas piping to stove / burner system locationStove Installation Stove Installation CSA-B149 1 or 2 Installation CodeNatural Gas Propane/LPInstalling Louvers Do not use open flame to check for gas leaksRemote Wall mounted Switch Electrical InstallationElectrical Wiring Installing logs and rock wool ember material in firebox Final InstallationFinal Installation Install Rock Wool Never use an open flame to check for gas leak Operating InstructionsWhat to do if YOU Smell GAS Never check for gas leak with open flame Approved leak testing methodOperating Instructions Pilot position Main burner switchLighting the burner Cleaning glass Firebox CleaningCleaning & Maintenance Venting systemAir shutter Adjustment Natural Gas only Adjusting the AIR ShutterAlways use gloves when handling Broken glassMake sure the glass panel edges do not Touch any metal parts during thermalBlower Wiring diagram for Blower BlowerTroubleshooting Observed Problem Possible Cause RemedyReplacement parts Fuel Conversion Kits SS38DVB,GN,P0Description Qty Natural Propane Venting Components DescriptionCarbon Monoxide Detector Requirements If Warranty Service is Needed Mhsc