PENINSULA INSTALLATION PROCEDURE

FRAMING

Note: In order to avoid the possibility of exposed insula- tion or vapour barrier coming in contact with the fireplace body, it is recommended that the walls of the fireplace enclosure be “finished” (ie: drywall/sheetrock), as you would finish any other outside wall of a home. This will ensure that clearance to combustibles is maintained within the cavity.

It is best to frame your fireplace after it is positioned. Use

2x4's and frame to local building codes.FIGURE 5.

A

FIGURE 5

COUNTERTOP / BAR INSTALLATION

When finishing the fireplace, combustible material may rest directly on of the top extension.

Note: Maximum weight tolerance is 400 lbs, provided that it is evenly distributed across the top extensions of the fireplace.

In order to achieve a countertop or bar type appearance with the minimum height allowed, framing must be non- combustible and may be done with metal studding at- tached to the heat shield sides or the upper frame of the fireplace. FIGURE 7.

FIGURE 7

A = 22 " minus finishing material thickness each side.

To install the fireplace face flush with the finished wall, position the framework to accommodate the thickness of the finished wall.

FIGURE 6

* The top extension may be removed if non-combustible framing is faced with a non-combustible material placed flush with the front face of the unit and extending from the top of the unit. (Example: cement board) (not supplied). Combustible counter / bar tops must maintain a minimum of 38 inches from the base of the fireplace to the underside of the top. Figure 8.

FIGURE 8

TOP EXTENTION

TOP OF THE UNIT

NOTE: Wolf Steel trim and/or surround kits will not to- tally cover the top extension of the fireplace. In order to obtain a smooth transition from the trim / surround to the wall, it is recommended that the top extension be removed and the unit be installed following the above procedure.

W415-0319 / D / 08.03.05

Image 8
Contents Unvented Millivolt System Table of Contents Napoleon GAS Fireplace Presidents Lifetime Limited Warranty Carbon Monoxide Poisoning MAY Lead to Death General InstructionsGeneral Information Determining Confined or Unconfined Space InstallationCombustion and Ventilation AIR Provisions GAS Installation Sided Framing Peninsula Installation ProcedureCountertop / BAR Installation Finishing Brick Panel InstallationFacing OPEN-END Installation Procedure = 25¼ minus finishing material thickness each sideSEE-THROUGH Installation Procedure Framing FacingIsland Installation Procedure LOG Placement FinishingMantle Installation Glowing EmbersCharcoal Embers HoodGvfl Installation L36 Louvre InstallationLogo Placement Heat Shield STAND-OFF RemovalDoor Opening and Closing GVF103-KT Patented Catalytic Door InstallationOptions Optional Blower Installation This Blower is not Recommended for the 4 Sided InstallationOperation / Maintenance For Your Safety Read Before LightingMaintenance Catalytic Tile MaintenanceOxygen Depletion Sensor Pilot Cleaning Venturi AdjustmentReplacements AccessoriesW415-0319 / D Trouble Shooting Guide Symptom Problem Test SolutionDo not Clean Glass When HOT Fireplace Service History