Heat & Glo LifeStyle SLR32 Termination Locations, A. Vent Termination Minimum Clearances

Page 22
6 Termination Locations

6 Termination Locations

A. Vent Termination Minimum Clearances

A. Vent Termination Minimum Clearances WARNING

Fire Risk.

Maintain vent clearance to combustibles as specified.

DO NOT pack air space with insulation or other materials.

Failure to keep insulation or other materials away from vent pipe may cause overheating and fire.

A

B

6 in. (minimum) up to 20 in.

18 in. minimum

152 mm/508 mm

457 mm

20 in. and over

0 in. minimum

Gas, Wood or Fuel Oil

Termination Cap

B

A *

2 FT. MIN.

GAS DIRECT VENT Manual background TERMINATION CAP

 

 

 

 

HORIZONTAL

 

 

 

 

20 INCHES MIN.

 

 

OVERHANG

 

 

 

VERTICAL

 

 

LOWEST

 

 

WALL

 

 

 

DISCHARGE

 

 

 

OPENING

 

 

 

X

12

Manual background ROOF PITCH

IS X/ 12

H (MIN.) - MINIMUM HEIGHT FROM ROOF TO LOWEST DISCHARGE OPENING

Gas

Termination

Cap **

*If using decorative cap cover(s), this distance may need to be increased. Refer to the installation instructions supplied with the decorative cap cover.

**In a staggered installation with both gas and wood or fuel oil terminations, the wood or fuel oil termination cap must be higher than the gas termination cap.

Figure 6.2 Staggered Termination Caps

Roof Pitch

H (Min.) Ft.

Flat to 6/12

1.0*

Over 6/12 to 7/12

1.25*

Over 7/12 to 8/12

1.5*

Over 8/12 to 9/12

2.0*

Over 9/12 to 10/12

2.5

Over 10/12 to 11/12

3.25

Over 11/12 to 12/12

4.0

Over 12/12 to 14/12

5.0

Over 14/12 to 16/12

6.0

Over 16/12 to 18/12

7.0

Over 18/12 to 20/12

7.5

Over 20/12 to 21/12

8.0

* 3 foot minimum in snow regions

Figure 6.1 Minimum Height From Roof To Lowest Discharge Opening

22

Heat & Glo • SLR32 • 2269-900 Rev. E • 4/12

Image 22
Contents •What to do if you smell gas NOTICEModel SLR32 Owner’s ManualA. Congratulations Homeowner Reference InformationInstaller Guide Table of ContentsSafety Alert Key 3 Maintenance and Service = Contains updated information 14 Appliance Setup15 Troubleshooting 13 FinishingWARRANTY COVERAGE B. Limited Lifetime WarrantyLIMITED LIFETIME WARRANTY WARRANTY PERIODWARRANTY EXCLUSIONS B. Limited Lifetime Warranty continuedWARRANTY CONDITIONS This warranty is void ifA. Appliance Certification D. High Altitude Installations1 Listing and Code Approvals B. Tempered Glass SpecificationsInstallation of Carbon Monoxide Detectors B. Your Fireplace A. Gas Fireplace Safety2 Operating Instructions User Guide WARNING! Choking Hazard! Keep glass rock mediaD. Decorative Doors and Fronts E. Fixed Glass AssemblyC. Clear Space G. Before Lighting FireplaceFOR YOUR SAFETY READ BEFORE LIGHTING H. Lighting Instructions IPIFinal inspection by LIGHTING INSTRUCTIONS IPIInitial Break-inProcedure J. Frequently Asked QuestionsI. After Fireplace is Lit •Some people may be sensitive to smoke and odorsGlass Cleaning 3 Maintenance and ServiceA. Maintenance Tasks-Homeowner Remote ControlVenting B.Maintenance Tasks-QualifiedService TechnicianGasket Seal and Glass Assembly Inspection FireboxInstaller Guide Getting StartedA. Typical Appliance System WALL SWITCHC. Tools and Supplies Needed B. Design and Installation ConsiderationsD. Inspect Appliance and Components 5 Framing and Clearances A. Selecting Appliance LocationB. Constructing the Appliance Chase Heat & Glo • SLR32 • 2269-900Rev. E • 4/12C. Clearances MINIMUM FRAMING DIMENSIONSNon-combustibleMantels D. Mantel and Wall ProjectionsCombustible Mantels Front Side Finishing DetailWALL Figure 5.8 Non-CombustibleZone5 IN SHEATHING6 Termination Locations A. Vent Termination Minimum ClearancesCovered Alcove Applications = AREA WHERE TERMINAL IS NOT PERMITTEDV= VENT TERMINAL X = AIR SUPPLY INLET A. Approved Pipe 7 Vent Information and DiagramsE. Vent Diagrams B. Vent Table KeyTop Vent - Horizontal Termination Venting with 1 elbowINSTALLED HORIZONTALLY 1. Top Vent - Horizontal Termination - continuedVenting with 2 elbows Top Vent - Horizontal TerminationVenting with 3 elbows 1. Top Vent - Horizontal Termination - continuedTop Vent - Horizontal Termination H2 V2 H1Exhaust restrictor Instructions Top Vent - Vertical Termination No ElbowsV1 = 44 ft. Max. 13.4 m PILOT HOLESSLR32 Top Vent - Vertical TerminationVenting with 2 elbows V1 MinimumSLR32 Venting with 3 elbowsTop Vent - Vertical Termination V1 MinimumV3 H2 H1 V1 Venting with 4 elbowsTop Vent - Vertical Termination V1 MINTable Coaxial to Colinear VentingPrior to installing the gas appliance Clearances to Combustibles•Vent this appliance directly outside TOP VENT•Use separate vent system for this appliance B. Wall Penetration Framing 8 Vent Clearances and FramingA. Pipe Clearances to Combustibles Between ceiling firestopsC. Install the Ceiling Firestop Flat Ceiling Installation D. Install Attic Insulation ShieldVaulted Ceiling Installation 9 Appliance Preparation A. Preparing Elbow Heat Shield•Sagging or loose insulation B. Securing and Leveling the ApplianceWARNING! Risk of Fire! Prevent contact with •Insulation backing or plastic10 Installing Vent Pipe SLP Pipe A. Assemble Vent SectionsC. Secure The Vent Sections B. Assemble Slip SectionsPilot hole E. Install Decorative Ceiling Components D. Disassemble Vent SectionsG. Assemble and Install Storm Collar F. Install Metal Roof FlashingCAULK Figure H. Install Vertical Termination CapI. Install Decorative Wall Components Figure 10.16 Wall ThimbleK. Install Horizontal Termination Cap Figure 10.17 Venting through the wallB. Gas Pressure 11 Gas InformationA. Fuel Conversion Access Through the Valve AssemblyValve Pressure Taps C. Gas ConnectionD. High Altitude Installations •Ensure adequate ventilationC. Optional Accessories Requirements A. Wiring RequirementsB. IntelliFire Ignition System Wiring 12 Electrical InformationD. Electrical Service and Repair E. Junction Box InstallationSetting the Fireplace into the Framing 13 FinishingA. Framing and Finishing Instructions Finishing InstructionsFigure 13.3 Finishing Details Heat & Glo • SLR32 • 2269-900Rev. E • 4/12Finish and Sealing Joints PaintingWallboard Joint-CrackPrevention and Repair Finishing Around Opening with Gypsum WallboardExtending Past The Face Of The Fireplace B. Mantel and Wall ProjectionsCombustible Mantel Legs Or Wall Projections Failure to comply could cause fireNon-CombustibleFinish Materials C. Facing Material0 - 1 inch thickness-OverlapFit Method Non-CombustibleFinish Material 0-4Inches Thick Non-CombustibleFinish Materials0 Inches to 4 Inches Thick-InsideFit Method 3/4 INTable 1. Dimensions of Martini Decorative Front D. Decorative FrontsTable 1. Dimensions of Tonic Decorative Front Figure 13.14 Dimensions of Tonic Decorative FrontC. Clean the Appliance 14 Appliance SetupA. Remove Fixed Glass Assembly D. Accessories• MEDIA-STONES-2 • SLR32-LOGS • MEDIA-CL2-GEMS • MEDIA-AMBER • MEDIA-BLACK • MEDIA-CLEAR• MEDIA-COBALT • MEDIA-BK2-GEMS • MEDIA-WH2-GEMS • GLASS32-LINERH. Air Shutter Setting F. Fixed Glass AssemblyG. Install the Mesh Removing Fixed Glass AssemblySymptom 15 TroubleshootingA. IntelliFire Ignition System Possible CausePossible Cause IntelliFire Ignition System - continuedSymptom Corrective ActionN R Q S P A. Appliance Dimension Diagram16 Reference Materials M K L J I Ø A B E F C D12-1/2in B. Vent Components Diagrams9 in 2-3/4inSLP-45- 45 Elbow B. Vent Components Diagrams continuedEffective Height Length SLP90- 90 ElbowSLP-CCS-BK B. Vent Components Diagrams continuedSLK-SNKD SLP-TVHWSLP-HRC-SS SLP-HRC-ZC-SS HORIZONTAL TERMINATION CAPOptional Wire Harness COAXIAL to COLINEAR VENTINGB. Vent Components Diagrams continued DESCRIPTIONSLR32 C. Service Partsat depot StockedC. Service Parts SLR32at Depot #11 Valve AssemblyC. Service Parts SLR32Stocked at DepotD. Contact Information NOTICE