Heat & Glo LifeStyle SLR32 owner manual A. Framing and Finishing Instructions

Page 49
13 Finishing

13 Finishing

A. Framing and Finishing Instructions

WARNING! Risk of Fire! Comply with all minimum clear- ances to combustibles as specified. Framing closer than the minimums listed must be constructed entirely of noncom- bustible materials (i.e., steel studs, concrete board, etc.)

Finishing Instructions

It is important to follow the framing and finishing instruc- tions to ensure proper placement of fireplace into the sur- rounding framing/finishing materials.

Wall sheathing materials 1/2 in. thick are specified in this installation manual to properly align with the factory- installed non combustible material.

WARNING! Risk of Fire! DO NOT remove the factory- installed non-combustible board or cover it with combus- tible material, such as:

Drywall (gypsum board)

Plywood

Materials that do not meet the ASTM E 136 Non-com- bustibility standard (below).

Removal of factory-installed, non-combustible board and/ or use of materials not meeting the ASTM E 136 standard may cause fire.

Non-Combustible Materials Specification

Material which will not ignite and burn. Such materials are those consisting entirely of steel, iron, brick, tile, concrete, slate, glass or plasters, or any combination thereof.

Materials that are reported as passing ASTM E 136,

Standard Test Method for Behavior of Materials in a Vertical Tube Furnace at 750 ºC and UL763 shall be

considered non-combustible materials.

Setting the Fireplace into the Framing

Unlike many traditional, single-sided Heat & Glo fireplaces, this fireplace is recessed into surround framing. The left and right nailing tabs were designed for the SLR32 model as a means to ensure the fireplace is recessed to the correct location within the framing materials.

1.Bend two nailing tabs away from fireplace 180 degrees on both left and right nailing tabs. Do not adjust the column standoffs. See Figure 13.1.

2.Screw each nailing tab to the adjoining framing mate- rial. Ensure that the 1 inch air space clearance is main- tained on the sides of the fireplace. See Figure 13.2.

FACTORY-INSTALLED

NON-COMBUSTIBLE BOARD

NAILING TABS

Figure 13.1 Nailing Tabs Installation Position

1/2 IN.

FRAMING

NAILING TAB

1/2 IN. FACTORY-SUPPLIED

NON-COMBUSTIBLE BOARD

Figure 13.2 Front Side Finishing Detail

Heat & Glo • SLR32 • 2269-900 Rev. E • 4/12

49

Image 49
Contents Model SLR32 NOTICE•What to do if you smell gas Owner’s ManualHomeowner Reference Information A. CongratulationsSafety Alert Key Table of ContentsInstaller Guide 3 Maintenance and Service15 Troubleshooting 14 Appliance Setup = Contains updated information 13 FinishingLIMITED LIFETIME WARRANTY B. Limited Lifetime WarrantyWARRANTY COVERAGE WARRANTY PERIODWARRANTY CONDITIONS B. Limited Lifetime Warranty continuedWARRANTY EXCLUSIONS This warranty is void if1 Listing and Code Approvals D. High Altitude InstallationsA. Appliance Certification B. Tempered Glass SpecificationsInstallation of Carbon Monoxide Detectors 2 Operating Instructions User Guide A. Gas Fireplace SafetyB. Your Fireplace WARNING! Choking Hazard! Keep glass rock mediaC. Clear Space E. Fixed Glass AssemblyD. Decorative Doors and Fronts G. Before Lighting FireplaceFinal inspection by H. Lighting Instructions IPIFOR YOUR SAFETY READ BEFORE LIGHTING LIGHTING INSTRUCTIONS IPII. After Fireplace is Lit J. Frequently Asked QuestionsInitial Break-inProcedure •Some people may be sensitive to smoke and odorsA. Maintenance Tasks-Homeowner 3 Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection B.Maintenance Tasks-QualifiedService TechnicianVenting FireboxA. Typical Appliance System Getting StartedInstaller Guide WALL SWITCHC. Tools and Supplies Needed B. Design and Installation ConsiderationsD. Inspect Appliance and Components A. Selecting Appliance Location 5 Framing and ClearancesHeat & Glo • SLR32 • 2269-900Rev. E • 4/12 B. Constructing the Appliance ChaseMINIMUM FRAMING DIMENSIONS C. ClearancesCombustible Mantels D. Mantel and Wall ProjectionsNon-combustibleMantels Front Side Finishing Detail5 IN Figure 5.8 Non-CombustibleZoneWALL SHEATHINGA. Vent Termination Minimum Clearances 6 Termination LocationsCovered Alcove Applications = AREA WHERE TERMINAL IS NOT PERMITTEDV= VENT TERMINAL X = AIR SUPPLY INLET E. Vent Diagrams 7 Vent Information and DiagramsA. Approved Pipe B. Vent Table KeyVenting with 1 elbow Top Vent - Horizontal TerminationVenting with 2 elbows 1. Top Vent - Horizontal Termination - continuedINSTALLED HORIZONTALLY Top Vent - Horizontal TerminationTop Vent - Horizontal Termination 1. Top Vent - Horizontal Termination - continuedVenting with 3 elbows H2 V2 H1V1 = 44 ft. Max. 13.4 m Top Vent - Vertical Termination No ElbowsExhaust restrictor Instructions PILOT HOLESVenting with 2 elbows Top Vent - Vertical TerminationSLR32 V1 MinimumTop Vent - Vertical Termination Venting with 3 elbowsSLR32 V1 MinimumTop Vent - Vertical Termination Venting with 4 elbowsV3 H2 H1 V1 V1 MINPrior to installing the gas appliance Coaxial to Colinear VentingTable Clearances to Combustibles•Vent this appliance directly outside TOP VENT•Use separate vent system for this appliance A. Pipe Clearances to Combustibles 8 Vent Clearances and FramingB. Wall Penetration Framing Between ceiling firestopsC. Install the Ceiling Firestop Flat Ceiling Installation D. Install Attic Insulation ShieldVaulted Ceiling Installation A. Preparing Elbow Heat Shield 9 Appliance PreparationWARNING! Risk of Fire! Prevent contact with B. Securing and Leveling the Appliance•Sagging or loose insulation •Insulation backing or plasticA. Assemble Vent Sections 10 Installing Vent Pipe SLP PipeC. Secure The Vent Sections B. Assemble Slip SectionsPilot hole D. Disassemble Vent Sections E. Install Decorative Ceiling ComponentsG. Assemble and Install Storm Collar F. Install Metal Roof FlashingCAULK I. Install Decorative Wall Components H. Install Vertical Termination CapFigure Figure 10.16 Wall ThimbleFigure 10.17 Venting through the wall K. Install Horizontal Termination CapA. Fuel Conversion 11 Gas InformationB. Gas Pressure Access Through the Valve AssemblyD. High Altitude Installations C. Gas ConnectionValve Pressure Taps •Ensure adequate ventilationB. IntelliFire Ignition System Wiring A. Wiring RequirementsC. Optional Accessories Requirements 12 Electrical InformationE. Junction Box Installation D. Electrical Service and RepairA. Framing and Finishing Instructions 13 FinishingSetting the Fireplace into the Framing Finishing InstructionsHeat & Glo • SLR32 • 2269-900Rev. E • 4/12 Figure 13.3 Finishing DetailsWallboard Joint-CrackPrevention and Repair PaintingFinish and Sealing Joints Finishing Around Opening with Gypsum WallboardCombustible Mantel Legs Or Wall Projections B. Mantel and Wall ProjectionsExtending Past The Face Of The Fireplace Failure to comply could cause fireNon-CombustibleFinish Materials C. Facing Material0 - 1 inch thickness-OverlapFit Method 0 Inches to 4 Inches Thick-InsideFit Method Non-CombustibleFinish MaterialsNon-CombustibleFinish Material 0-4Inches Thick 3/4 INTable 1. Dimensions of Tonic Decorative Front D. Decorative FrontsTable 1. Dimensions of Martini Decorative Front Figure 13.14 Dimensions of Tonic Decorative FrontA. Remove Fixed Glass Assembly 14 Appliance SetupC. Clean the Appliance D. Accessories• MEDIA-COBALT • MEDIA-BK2-GEMS • MEDIA-WH2-GEMS • MEDIA-AMBER • MEDIA-BLACK • MEDIA-CLEAR• MEDIA-STONES-2 • SLR32-LOGS • MEDIA-CL2-GEMS • GLASS32-LINERG. Install the Mesh F. Fixed Glass AssemblyH. Air Shutter Setting Removing Fixed Glass AssemblyA. IntelliFire Ignition System 15 TroubleshootingSymptom Possible CauseSymptom IntelliFire Ignition System - continuedPossible Cause Corrective Action16 Reference Materials A. Appliance Dimension DiagramN R Q S P M K L J I Ø A B E F C D9 in B. Vent Components Diagrams12-1/2in 2-3/4inEffective Height Length B. Vent Components Diagrams continuedSLP-45- 45 Elbow SLP90- 90 ElbowSLK-SNKD B. Vent Components Diagrams continuedSLP-CCS-BK SLP-TVHWHORIZONTAL TERMINATION CAP SLP-HRC-SS SLP-HRC-ZC-SSB. Vent Components Diagrams continued COAXIAL to COLINEAR VENTINGOptional Wire Harness DESCRIPTIONat depot C. Service PartsSLR32 Stockedat Depot SLR32C. Service Parts #11 Valve AssemblyStocked SLR32C. Service Parts at DepotNOTICE D. Contact Information