INSTALLATION
HORIZONTAL
INSTALLATIONS
Install the vent system according to the manu- facturer's instructions included with the com- ponents.
1)Set the unit in its desired location. Check to determine if wall studs or roof rafters are in the way when the venting system is attached. If this is the case, you may want to adjust the location of the unit. Rough in the gas preferably on the right side of the unit and the electrical (junction block is on the left side) on the left.
2)Direct Vent pipe and fittings are designed with special
3)Put a bead of silicone inside the outer section of the adapter and a bead of Stove Mate on the inner collar. Slip the adapter over the existing inner and outer flue collar and fasten to the outer collar only with the 3 supplied screws (drilling pilot holes will make this easier). Level the fireplace and fasten it to the framing using nails or screws through the nailing strips.
4)Assemble the desired combination of pipe and elbows to the appliance adaptor and
They may be located by examining the inside of the female ends.
Note: Apply sealant
b)Horizontal runs of vent must be sup- ported every 3 feet (0.9meter). Wall straps are available for this purpose.
5)Mark the wall for a 11" x 11" (279mm x 279mm) square hole. The center of the square hole should line up with the center- line of the horizontal pipe. Cut and frame the 11 inch (279mm) square hole in the exterior wall where the vent will be terminated.
If the wall being penetrated is constructed of
Diagram 5
The four wood screws provided should be replaced with appropriate fasteners for stucco, brick, concrete, or other types of sidings.
7)Before connecting the horizontal run of vent pipe to the vent termination, slide the Wall Thimble (Part # 1247) over the vent pipe.
8)Slide the appliance and vent assembly to- wards the wall carefully inserting the vent pipe into the vent cap assembly. It is impor- tant that the vent pipe extends into the vent cap sufficient distance so as to result in a minimum pipe overlap of
Note:
a)
Diagram 1
Diagram 2
Note:
a)The horizontal run of vent must be level, or have a 1/4 inch rise for every 1 foot of run towards the termination. Never allow the vent to run downward. This could cause high temperatures and may present the possibility of a fire.
b)The location of the horizontal vent ter- mination on an exterior wall must meet all local and national building codes, and must not be blocked or obstructed. For External Vent Terminal Locations, see diagram on page 11.
6)The arrow on the vent cap should be pointing up. Insure that the
Note: If installing termination on a siding covered wall, a vinyl siding stand- off or furring strips must be used to ensure that the termination is not recessed into the siding.
Diagram 6
9)Install wall thimble in the center of the 11" (279mm) square and attach with wood screws (Diagram 7).
Diagram 7
20 | Regency P48 Zero Clearance Direct Vent Gas Fireplace |