Sherwood EG40 DV owner manual End of the pipes and fittings, are

Page 21
Figure 24: Twist-Lock Connection

Initial Installation

QUALIFIED INSTALLERS ONLY

HORIZONTAL INSTALLATION:

1.Set the appliance in the desired location. Check to determine if wall studs or roof rafters are in the way when the venting system is attached. If this is the case, you may want to adjust the location of the appliance.

2.Direct vent pipe and fittings are designed with special twist-lock connections. Assemble the desired combination of black pipe and elbows to the appliance adapter with pipe seams oriented towards the wall or floor, as much out of view as possible.

Place a bead of Mil-Pac on the outer edge of the inner exhaust pipe (non-flared end). Place a bead of high temperature silicone on the male edge of the outer pipe. Push the pipe sections completely together, then twist-lock one section clockwise approximately 1⁄4 turn, until the two sections are fully locked. The female locking lugs will not be visible from the outside, on black pipe. They may be located by examining the inside of the female ends as shown in Figure 23.

Notes:

Twist-lock procedure: four (4)

 

indentations, located on the female

Female

end of the pipes and fittings, are

Locking

designed to slide straight onto the

Lugs

Sealant

male ends of adjacent pipes and

fittings, by orienting the four pipe

 

Male

indentations so they match and slide

Locking

into the four entry slots on the male

Lugs

 

end.

• Horizontal runs of vent pipe must be supported every three ft. Wall straps are available for this purpose, also

when running horizontal pipe minimum clearances to combustibles must be maintained; 2 inches (5.1 cm) at top, 11⁄2 inches (3.8 cm) at sides, 11⁄2 inches (3.8 cm) at bottom.

���

�������

���

�������

Figure 25: Wall Framing Hole for Horizontal Installation.

11/4"

 

(3.2cm)

 

Fold strap

Woodscrews

 

here

 

Sheet metal

 

screws

 

 

Wall Thimble

 

Strap

Figure 26: Installing Decorative Wall Thimble.

3. With the pipe attached to the stove in the correct location, mark the wall for a 10” (25.4 cm) x 10” (25.4 cm) square hole (refer to Figure 25). The center of the square hole should match the center line of the

horizontal pipe. Cut and frame the 10” (25.4 cm) x 10”

(25.4 cm) hole in the exterior wall where the vent will be terminated. If the wall being penetrated is constructed of non-combustible material i.e. masonry or concrete, a 7 inches (17.8 cm) hole is acceptable.

21

Image 21
Contents EG40 DV General Safety PrecautionsTable of Contents Vented GAS Fireplace Heater EG40 DV NG/LPG Codes And ApprovalsEG40 Exterior Dimensions SpecificationsOperating Instructions For Your Safety Read Completely Before OperatingComponent Sound & Reason There is a separate venturies for each burner, see FigureRemoving the Door Maintenance and ServiceBurner is lined up Conversion Kit Installation Kit Parts ListRemoving valve Screw Must be not visibleQualified Installers only Initial InstallationCommon Vertical Installation Do not interfere with the structural integrity of the walls Vent Termination Restrictions KIT Components Assembly of Venting Kit Manufacturer Trade Name Nominal Sizes SV4EBR45 Vent restrictor ring End of the pipes and fittings, are Installing Vent Cap with Vinyl Siding Stand-Off Assemble the desired lengths of black pipe Use of Wall Straps Insulation Multi-Story Vent Pipe Installation33a-2002 Test Methods and the Resulting ITS/WH Must be bolted securely to the floor Must be connected to a grounding rodRear Burner Natural Gas Propane Front BurnerManifold Pressure Min. Manifold PressureLog Placement Secondary InstallationRemove door to clean glass Problem Possible Cause Solution Trouble ShootingT. Nova Valve Convertible 50-1421 Parts ListParts List Parts Diagram Chassis Parts Diagram Gas Tray & Door To the Dealer WarrantyWarranty Warranty Installation Data Sheet