APPLICATION INSTRUCTIONS

S-2299

APPLICATION INSTRUCTIONS FOR TOTAL CONCEPT CLEANING OF BOILER

SIZE: 1 Gallon PART NUMBER: 20 - 0307

GENERAL NOTES:

Market Forge R has two basic types of boilers; one has an automatic drain valve, the other has a manual drain valve. To determine which type you have, open cabinet doors and you will see a control box with two switches and an indicator light. The instruction label on the control box will identify the boiler as being either automatic or manual. Those boilers designated as being automatic must be energized in order to close the drain valve.

Total Concept is designed to be used with water between 160°F to 200°F.

Preheating is required on both automatic and manual boilers to raise the water temperature to the acceptable range. (160°F to 200°F).

For manual boilers, make certain drain valve is tightly closed.

On Market Forged boilers manufactured after 8/84; your unit is equipped with an access plug in the steam header line. This location should be used to add cleaner/des- caler to boiler chamber during maintenance.

On Market Forged boilers manufactured before 8/84; ac- cess to boiler chamber should be gained through either the vent-rite or the pressure relief valve.

Total Concept is a NSF listed nonfood product. This is a liquid acid (nonmuriatic) product that works without fumes, odors, and hazards associated with other harsh chemicals.

BOILER TREATMENT CLEANING INSTRUCTIONS: After determining proper location for cleaner/descaler to be added: Read complete instructions thoroughly; in- cluding all warning and cautionary statements.

Fig. 1

1. Energize boiler and fill to operating level.

Fig. 2

2. Energize heating circuit to pre-heat unit.

Fig. 3

Fig. 4

3.AUTOMATIC - After unit is pre-heated, cycle the pow- er switch to the OFF position then immediately back to the ON position.

22

Image 25
Contents GAS Operated Boiler Table of Contents Introduction Introduction HOW to USE this ManualTo the Kitchen Manager Theory of Operation for GAS BoilerInstalling Legs Installation InstructionsGAS Operated Boilers Models LevelingElectric Service Connection GAS Service ConnectionsGas Operated Boilers Service ConnectionsLower Deflector Assembly First Check to be Sure That Operating InstructionsIf GAS Pressure is LOW AdjustmentsIf GAS Pressure is TOO High Pressure Control Switch Adjustment Setting the Boiler Control Pressure SwitchesTrouble Possible Cause Remedy General TROUBL-SHOOTINGGeneral TROUBL-SHOOTING Water Control Board Testing Procedure Testing ProcedureItem no Part Description Illustrated Parts ListPressure Switch Box Control Box Assembly, with and without Cover Plumbing, Left Side Gas Boiler Front View Gas Boiler, 24, 200K Gas Train, 200K BTU Boiler Shown Gas Train, 200K Boiler Shown Electrical Information Electrical Information Cleaning the Boiler MaintenanceCleaning Instructions Maintenance General Notes Application InstructionsDo not Reuse Container