G. Cut out Hole in Roof

Refer to Figure 8.9.

Plumb from roof to center of chimney.

Drive a nail up through roof to mark center of pipe.

Measure to either side of nail and mark the 17 in. x 17 in. (432 mm x 432 mm) opening required.

Measure opening on the horizontal; actual length may be larger depending on roof pitch.

Cut out and frame opening.

Refer to Chapter 25 of the Uniform Building Code for roof framing details.

H. Complete Installation

WARNING! Risk of Fire! You MUST maintain 2 in.

(51 mm) air space to insulation and other combustible materials around the chimney system. Failure to do so could cause overheating and fire.

Keep chimney sections from separating or twisting.

You may secure straight chimney sections at the joints with screws no longer than 1/2 in. (13 mm).

The following steps should be skipped if using a chase.

Install roof flashing appropriate to roof pitch.

Install round termination cap and storm collar.

I. Install Flashing

Assemble chimney so it passes through the framed opening.

Slip the flashing over the chimney.

NOTICE: Roofing shingles must be below the flashing plate on the lower side of a sloped roof and over the flashing plate on the sides and top.

Nail the flashing to the roof. Keep gaps between the flashing plate and the roof to a minimum.

Caulk the flashing plate and roof junction as well as the vertical seam on the flashing. All nail heads must be caulked with a roofing sealant.

Figure 8.9 Ceiling/Attic Construction

32

Heat & Glo • EXCLAIM-36, EXCLAIM-424013-251 Rev C • 11/08

Image 32
Contents Fire Risk Wood Burning FireplaceHot screen/mesh and glass doors will cause burns Number Listing Label Information/LocationGrate User Guide Table of ContentsInstaller Guide Warranty Hearth & Home Technologies Limited Warranty CONDITIONS, Exclusions & Limitation of LiabilityHeat & Glo EXCLAIM-36, EXCLAIM-42 4013-251 Rev C 11/08 Listing and Code Approvals Appliance CertificationNon-Combustible Materials Combustible MaterialsHot glass will cause burns Operating InstructionsYour Fireplace Seasoned Wood Starting a FireGrate FirescreenGlass Doors Vented Gas Log Sets & Gas Log LightersOptional Components Clear SpaceWood Fuel Maintainance and Service Chimney Inspection/CleaningDisposal of Ashes Creosote Formation and Need for RemovalGlass Cleaning Check Firebox RefractoryInspect Grate Frequency As desiredTroubleshooting Guide Start Fire Problems Possible Cause SolutionGetting Started Typical Fireplace SystemNegative Pressure Design and Installation ConsiderationsDraft Locating Fireplace & Chimney Frequently open doors Central heat outlets or returnsInspect Fireplace and Components Tools and Supplies NeededFireplace System Requirements Framing & Clearances Select Fireplace LocationClearances Clearances to Combustible MaterialsSidewalls/Surrounds Frame the FireplaceInstallation of Fireplace Unpack the Fireplace EXCLAIM-42 onlyThings to Consider Unpack the Fireplace EXCLAIM-36 onlyPosition the Fireplace EXCLAIM-42 only Removing Smoke ShieldInstall the Refractory EXCLAIM-42 only GAS KnockoutPlace Protective Metal Hearth Strips Level FireplaceInstall Outside Air Kit YESChimney Assembly Chimney Requirements Height of Chimney ComponentsUsing Offsets/Returns ExampleInstall Chimney Air Kit Assemble Chimney SectionsInstall Ceiling Firestops Installing the Ceiling FirestopInstall Attic Insulation Shield 330 mmComplete Installation Install FlashingFollowing steps should be skipped if using a chase Cut out Hole in RoofChimney Termination Requirements Flat RoofsChase Installations Construct the ChaseInstall Fireplace & Chimney Install Chase TopInstall Termination Cap ST1175/ST475 Square Termination CapTCT1175 Terra Cotta Cap Shrouds Radiation ShieldField Constructed Shrouds Open Top Shroud TR11/TR11T caps require radiation shieldMailbox Style Shroud radiation shield required Roofed Style Shroud radiation shield required= 1/k x inches of thickness FinishingHearth Extension Raised Hearth Extension Framing Hearth Extension ConstructionNon-combustible Sealant Flush Hearth Extension FramingFinishing Material Noncombustible FacingCombustible Mantel 19 3/4 502 mm Accessories Gas Log/Lighter ProvisionWood Burning Inserts Gas Code, Ansi Z223.1Fireplace Dimensions Reference MaterialsEXCLAIM-36 EXCLAIM-42 Chimney Components Catalog #15-1/4 387 mm 15-3/4 400 mm CT56 Chase Top LDS33/LDS46 Decorative Shroud Service Parts EXCLAIM-36H, EXCLAIM-36TEXCLAIM-42H, EXCLAIM-42T This page intentionally left blank Do not Discard this Manual