Hearth and Home Technologies SOHO-CE manual Assembling and Installing Storm Collar, Sharp Edges

Page 21

Assembling and Installing Storm Collar

CAUTION

Sharp Edges

Wear protective gloves and safety glasses during installation.

Connect both halves of the storm collar with two screws (see Figure 8.6).

Wrap the storm collar around the exposed pipe section and align brackets. Insert a bolt (provided) through the brackets and tighten nut to complete storm collar assembly (see Figure 8.7).

Slide the assembled storm collar down the pipe section until it rests on the roof flashing.

Caulk around the top of the storm collar (see Figure 8.5).

Figure 8.7 Assembling the Storm Collar Around the Pipe

Figure 8.6 Assembling the Storm Collar

Heat & Glo • Soho-CE2111-900 Rev. D • 6/07

21

Image 21
Contents What to do if you smell gas Model Soho-CEHomeowner Reference Information CongratulationsTable of Contents Appliance Certification Listing and Code ApprovalsNon-Combustible Materials Specification Combustible Materials SpecificationGetting Started Design and Installation ConsiderationsInspect Appliance and Components Tools and Supplies NeededFraming and Clearances Selecting Appliance Location84.1 74.0 118.7 89.2 Clearances Constructing the Appliance ChaseFlue Termination Minimum Clearances Termination LocationsSee .4 for specific clearances Cm minimum in snow regionsAlcove Applications Flue Table Key Flue Information and DiagramsUse of Elbows Measuring StandardsOne Elbow Minimum Maximum Flue Diagrams Horizontal Termination One Elbow Two Elbows+ H Maximum = 11.9 m Maximum = 4.6 m Two Elbows Minimum + H 2 Maximum Elbow only Not AllowedHorizontal Termination Three Elbows Three Elbows Minimum Maximum+ V 2 + H = Maximum = 11.9 m + H 2 Maximum = 4.6 m V1 = 11.8 m Maximum Vertical Termination No Elbow Two ElbowsTwo Elbows V1 Minimum Maximum V1 + V2 + H Maximum = 11.9 mVertical Termination Three Elbows Three Elbows V1 Minimum H1 + H2 Maximum+ V2 + H1 + H2 Maximum = 11.9 m Maximum = 4.3 m Pipe Clearances to Combustibles Flue Clearances and FramingWall Penetration Framing Combustible Wall PenetrationInstalling the Ceiling Firestop Installing Attic ShieldVertical Penetration Framing Securing and Leveling the Appliance Appliance Preparation Assembly of Flue Sections Installing Flue Pipe Install Support Brackets Attach the First Flue Component to Starting CollarsInstalling Firestops and Horizontal Termination Cap Installing the Horizontal Termination CapFor Horizontal Runs Wall shield firestops are Required Install Roof Flashing and Vertical Termination Cap Sharp Edges Assembling and Installing Storm CollarGas Pressure Requirements Gas InformationGas Connection Natural Gas Propane Butane G20 G31 G30 G25Electrical Information Electronic Ignition System WiringFacing Material FinishingMantel Projections See for combustible/non-combustible definitionsClean the Appliance Appliance SetupAccessories Ember PlacementPositioning the Logs Log Assembly LOGS-SOHOCEGlass Assembly Removing Glass AssemblyReplacing Glass Assembly Before Lighting Appliance Operating InstructionsElectronic Ignition Lighting the FireplaceFrequently Asked Questions Initial Break-in ProcedureAfter Appliance is Lit Symptom Possible Causes Corrective Actions TroubleshootingElectronic Ignition System No transmission, motor Receiver mustMaintaining and Servicing Appliance Maintenance TasksRecommend addition of screen if one is not present Inspect Maintenance TasksVerify no obstructions to airflow through the louvers Operating properly. Replace as necessaryAppliance Dimensions Table Appliance Dimension DiagramReference Materials Location CentimeterService Parts List Log Set Assembly108 SOHO-CE SOHO-CE Service PartsLimited Lifetime Warranty Heat & GLO GAS Appliance Products Limited Lifetime WarrantyImportant operating Contact Information