State Industries SBN85390NE/A warranty Sequence of Operation

Page 23

SEQUENCE OF OPERATION

The following information will describe the Sequence of Operation for this appliance.

1.Switch power on to unit.

2.Thermostat calls for heat.

3.Ignition Control Board performs diagnostic check on system components.

4.On completion of diagnostics check, the Ignition Control Board sends signal to Exhaust Inducer.

5.Exhaust Inducer begins drawing air through appliance closing the Prover Switch.

6.On completion of Prover Switch engagement, the Ignition Control Board begins the ignition cycle.

7.The Ignition Control Board provides power to the Silicon Nitride Ignitor.

8.The Silicon Nitride Ignitor heats up for approximately 17 to 20 seconds.

9.At the end of Silicon Nitride Ignitor’s warm-up, the Ignition Control Board opens the Gas Valve.

10.From the time the Gas Valve opens, the Ignition Control Board waits 3 seconds and then shuts off power to the Silicon Nitride Ignitor.

11.From the time the Silicon Nitride Ignitor’s power is shut off, the Ignition Control Board waits 3 more seconds to monitor the Flame Sensor.

12.If the Flame Sensor does not detect a strong enough flame, the Ignition Control Board shuts off the Gas Valve and allows the Exhaust Inducer to purge the unit for 20 seconds. At that time, the Ignition Control Board restarts with step 7. It will try and ignite the main burners 2 more times. If the unit does not light, the Ignition Control Board will wait one hour and then restart at step 3. This cycle will continue until the unit lights or the power is shutoff to the unit.

13.If the Flame Sensor detects a strong flame, the Ignition Control Board will allow the unit to operate until the thermostat is satisfied.

14.Once the unit is satisfied, the Ignition Control Board will shut off the Gas Valve and the unit will be in standby mode until another call for heat is initiated by the thermostat.

See the flow chart on page 31 for more information.

23

Image 23
Contents Models SBN71120NE Thru SBN85390NE/A Series Gasand Electrical Characteristics ROUGH-IN-DIMENSIONSFront View TOP View Back View ROUGH-IN-DIMENSIONS Foreword Table of ContentsGeneral Safety Information High Limit Switch FeaturesHigh Altitude Installations SELF-CLEANING Hydro CannonUncrating Exhaust Inducer Blower AssyCirculating Pump Dishwashing Machine RequirementBack Ceiling Side LevelingClearances Model RightUnconfinedspace Hard WaterAIR Requirements VentingType B GAS Vent Technical Data VentingTechnical Data Venting Relief Valve Multiple Heater ManifoldWater Line Connections Water Potable Heating and SpaceCode Restrictions Installation DIAGRAMS-TOP INLET/OUTLET UsageTube Inlet Installation GeneralHorizontal Storage Tank and Forced Circulation Vertical Storage Tank and Forced CirculationPage Circulating Return Line Connection Installation DIAGRAMS-SIDE INLET/OUTLET UsageHeater with Mixing Valve and Recirculated Sanitizing Loop TWO PRE-HEATERS with Booster Heater Horizontal Storage Tank Three Unit Manifold KIT Four Unit Manifold KIT Model Dimension aManifold Kits TWO Unit Manifold KITSingle Unit Wiring Diagram SBN-120 Through 400A Heater WiringPurging GAS Pipingand Dirt LEG InstallationGAS Piping GAS Pressure RegulatorFilling OperationManifold GAS Pressure in Inches Water Column ALL Models Sequence of Operation Operating Instructions For Your Safety Read Before OperatingLighting and Operation Instructions Ignitor Assembly Preventive MaintenanceWater Temperature Control Check the Ignitor AssemblyChecking the Input Main BurnerGAS Valves Anode ROD Inspection Remote Storage Tank Temperature ControlVenting System HOT Water OdorDeliming Solvents Tank Cleanout ProcedureDeliming Using FLO-JUG Method Electrical Servicing ServiceSystem Diagnostics Ignition Module SystemYES Replacement PARTS, Service Handbooks and Training AidsSequence of Operation Flow Chart Complaint Cause User Serviceman Operational ChecklistLindahl Parkway Ashland City, TN Phone 800-821-2017 Fax