Installation

5.Mount the block-off plate using masonry screws in a masonry fireplace and sheet metal screws on a zero- clearance fireplace (screws need only be long enough to penetrate the first layer of metal).

6.Insulate the block-off plate

using high-temperature fiberglass insulation and furnace cement.

Damper must be removed

Zero-clearance (metal) firebox

IMPORTANT:

DO NOT modify any part of the ZC fireplace

Mantel

Stainless steel chimney connector must extend 12" (305mm) past the block-off plate.

Block-off plate or damper adaptor.

Surround Panel

USA 16” (406 mm)

CND 18” (450 mm)

Figure 40: Insert Install into a Zero-Clearance Fireplace.

Damper removed or fastened open

Mantel

The stainless steel

chimney connector must

extend 12" (305mm) past the block-off plate.

Block-off plate or

damper adaptor. Surround Panel

USA 16” (406 mm)

CND 18” (450 mm)

Masonry Fireplace

Figure 41: Masonry Fireplace Direct Connection Insert Install.

7.After installing the unit into place and the pipe through the block-off plate, use high-temperature fiberglass insulation and furnace cement to seal any gaps between the pipe and block- off plate (allow the cement to dry for at least 24 hours before burning).

Before starting this type of installation

refer to INSTALLATION - MASONRY FIREPLACE INSTALLATION - INSERT for additional

information. For clearances refer to

SPECIFICATIONS - CLEARANCES TO COMBUSTIBLES -

1200 INSERT and SPECIFICATIONS - CLEARANCES

TO COMBUSTIBLES - 1700 INSERT. See Figure

40 and 41 for examples of a masonry fireplace and a zero-clearance fireplace with a direct connection

34

Image 34
Contents Wood Stove Table of Contents Safety Precautions Operating Instructions First StartReplacing the Glass Maintenance Helpful Hints Worth Repeating What does dry, seasoned wood mean? Air Control Rod 1200 Air Flow Path Specifications Capacity Feet3 0.0708 meter3 Approximate heating area † From front of door opening to edge of floor protection Maintain These Minimum Clearances to Unshielded Combustibles 1700 Freestanding Clearance to Combustibles 1200 Insert Dimensions 1700 Insert Dimensions 1200 Freestanding Flat Top Dimensions 1700 Freestanding Flat Top Dimensions 1200 Freestanding with Fan Kit Dimensions Installation Bolts to removeInstalling Heat Shield Recommended Height for Flue Pipe Chimney Through Wall Method a Roof Clearances Any area within 10 feet Installation into a masonry chimney Venting Outside AIR Insert Installation into existing fireplace with Hearth Metal TAG this Fireplace has Been Before starting this type of installation 3D of Dimensions needed from Fireplace Insert Install into a Zero-Clearance Fireplace Total Bricks Tube C Tube B Tube a Do not USE Door if Glass is Broken Installation of Ceramic Baffle Back View of Freestanding Unit with Fan Kit Removal of right Pod Installation of Trim Parts List EFW-264 PartsDiagramFreestanding Parts Diagram Pedestals & Legs Parts Diagram Fireplace Insert Warranty Limited Five 5 Year Warranty Limited One 1 Year WarrantyExclusions and Limitations Warranty Installation Data Sheet