A.O. Smith 403, 400, 402 Status Displayed True Condition Input, Menu Screen, Temperature Screen

Page 39

The following status information is displayed from the System Status Screen:

Status Displayed

*(True Condition)

Input

Output

ECO

Outlet temperature too high

open

- - - -

LW/CO

Water Level low

open

- - - -

Blk Flue

Flue blocked

open

- - - -

Flow

Water flowing

closed

- - - -

Low Gas

Gas pressure low

open

- - - -

Tstat

Thermostat requesting heat

closed

- - - -

Hi Limit

Outlet temp exceeds High Limit setpoint

- - - -

- - - -

Pump

Pump output activated

- - - -

On

IRI Gas Pwr

IRI output relay activated

- - - -

On

IRI Gas

IRI Gas Valve on

closed

- - - -

Pwr Vent

Power Vent running

closed

- - - -

Alarm

Alarm output activated

- - - -

On

Pwr Vent Pwr

Power Vent output relay activated

- - - -

On

 

- - - - STAGES 1 to 2 - - - -

 

 

BlwHi Prv

Blower pressure sufficient

closed

- - - -

Blw Hi

Blower High output activated

- - - -

On

BlwLo Prv

Blower pressure sufficient (not used at this time)

closed

- - - -

Blw Lo

Blower low output activated (not used at this time)

- - - -

On

Ignt Cur

Igniter current sufficient for ignition

- - - -

- - - -

Ignit

Igniter output is activated

- - - -

On

Gas Relay

Gas output relay activated

- - - -

On

Hi Gas

Gas pressure too high

open

- - - -

Flame

Flame detected

- - - -

- - - -

Menu Screen:

Displayed when the user presses the "Menu" key. This screen is the selection point for the other 9 screens.

Temperature Screen:

Displays the sensed temperatures of the Outlet, Inlet, and Tank probes. Also displayed is the calculated Delta T (Outlet minus Inlet) for the system. Shorted ("Short") and disconnected ("----") probes are also displayed.

System Status Screen:

This screen is used to view the status of switch inputs and output states. An asterisk (*) is displayed next to the label when the status is "True" (the description is fulfilled). For example, if water is flowing, or detected by the flow sensor, then an "*" will appear in front of the Flow label (i.e. *Flow). Another example would be the ECO switch. If the outlet temperature is too high the display will show: *ECO.

NOTE: The LWCO, IRI Gas Valve, Powered Vent, High Gas, and Low Gas inputs are optional inputs. Flame sensing, Igniters, and Blowers are optional on Stages 2, 3 and 4. (Except on a 4-stage system, stage 2 always has an Igniter, Blower, and Flame Sensor. Those dipswitches on stage 2 are not relevant.) One or two speed blowers can be used on any stage.

The System monitors the inputs at these times:

ECO, LWCO, Blocked Flue, Low Gas, Hi Limit, and Hi Gas - at all times for a fault condition.

Tstat - at all times for open/closed conditions.

IRI Gas and Powered Vent - for an on condition when their outputs (Pump, IRI Gas Pwr, Powered Vent Power) are turned on and an off condition at all other times.

Flow - for an on condition when the pump is on (no check for off state)

Blower Prover - when the Blower is on.

Igniter Current - for an on condition approximately 18 seconds

after the Igniter is turned on until the igniter is turned off and an off condition at all other times.

Flame - for an on condition approximately 5 seconds after the gas valve is turned on until the valve is turned off and at all other times for an off condition.

Control Status Screen:

Displays the status that the CCB and FCB micros are in. The CCB has 5 possible states and the FCB's have 9. The normal CCB states sequence is to move from Idle, to Pre-Circulate, then to Heating Stage 1-2-3-4 when a call for heat is initiated. Once heat has been satisfied or the Thermostat is opened, the sequence moves to Post- Circulate and then back to Idle. If a fault occurs at any time, the process jumps out of sequence and goes directly to the appropriate Hard or Soft Fault state.

Description of CCB control states:

Idle:

The yellow "Standby" LED is turned on and the system waits for a heat request (determined by the Thermostat or controlling probe inputs). All outputs are off in this state except that if the Post-Circulate time is set to continuous, the pump will be on. When the heat request is received, the system moves to the Pre-Circulate state.

Pre-Circulate:

The yellow LED is turned off and the green "Running" LED is turned on. The green LED will remain on for all other states except the fault states. If enabled the powered vent and the IRI gas valve are turned on. A command is sent to all active stages to cold purge the system. Cold purging clears out any combustion gas that may be in the combustion chamber. When purging is complete the system moves to the Heat State.

Heat Stages 1-2-3-4:

The system will command the FCB micros to start their heat sequence starting with stage 1. Stage 2, 3, 4 will be activated in order based on an algorithm that determines how much heat is needed. The system will remain in this state until the heat request is satisfied, the Tstat is opened, or a fault occurs.

39

Image 39
Contents Copper Boilers for Hydronic Heating HOT Water Supply Installation Operation Maintenance Limited WarrantyDIMENSIONS/CAPACITIES Data Dimensional DataGAS and Electrical Requirement Dimensions Data for Outdoor Configuration Foreword Recovery CapacitiesFEATURES/CONTROLS ON/OFF Switch Differential Pressure Switch Combustion AIR BlowerBlocked Flue Pressure Switch Water Flow SwitchLocation Installation InstructionsSafety Relief Valves Required AbilityAIR Requirements Installation ClearancesChemical Vapor Corrosion LevellingVenting Horizontal Vent Installation General System InstallationInstallation AS Boiler Replacement INTAKE/EXHAUST Installation Requirements16 40.6 cm Standard Vent Vertical CategoryType B or EquivalentIII Standard Vent Horizontal CategoryIII Stainless SteelDirect Vent Vertical Category Direct Vent Vertical Exhaust ConfigurationsStainless GAL.STEEL Direct Vent Horizontal Exhaust ConfigurationsDirect Vent Horizontal Category Stainless GAL. Steel SealedHydronic Installation Space Heating Applications Internal ContaminantsVAC System Controller Optional Tank Probe Optional Tank Probe Installation ProcedureGAS Connections Water Line Connections Hard Water ConditionsSingle boiler with horizontal tank Single boiler with vertical tank Suggested Pipe Size For Multiple Gas Appliances Propane Gas BTU/HR Single Unit INSTALLATION, Suggested Pipe SizeWiring Connections Distance from Meter BTU InputGAS Manifold Assembly Genesis GB/GW 1000-2500 Series 400 Wiring Diagram Page Genesis GB/GW 1000-2500 Series 400 Schematic Diagram Page CCB Central Control Board FCB Flame Control Board Diagram PDB Power Distribution Board Diagram Inlet GAS Pressure OperationFilling and Purging Water System Purging of GAS LineFor Your Safety Read Before Operating For Your Safety Read Before Operating Control System AdjustmentsRisk of Scalds Temperature Setting Degree Burns on Adult SkinCCB/FCB Indicator Lamps & Fuses Air Pressure Sensors open condition indicates faultGas Pressure Sensors open condition indicates fault Water Level Sensor open condition indicates faultCCB-SW2 CCB Ten Position Dipswitch Central Control Section SW1Operating Sequence FCB Eight-Position DipswitchUIM Screens Temperature Setpoints System Control AlgorithmUIM Operating Procedures Stages 1 and 2 will turn on in sequence from 1 toSystem Status Screen Temperature ScreenStatus Displayed True Condition Input Menu ScreenDescription of FCB control states Operating Setpoint Adjustment Procedure High Limit Differential Setpoint Adjustment ProcedureOperating Differentialsetpoint Adjustment Procedure Fault Displayed Description Redled Lockout Hard Tank Probe Tank Remote probe shorted or open Flashing Main BurnersDeliming Tubecleaningprocedure Mechanical Removal of Deposits Replacement PartsConditions and Exceptions NEW Boiler Limited WarrantyTennessee Waltz Parkway, Ashland City, TN Phone