AIR MOVEMENT RECORDINGS
(Supplement to Ventilator Installation/Start Up Report)
Project Name
| Readings Taken by: | ||
A. ENERGY AIRE HOODS - EXHAUST |
|
|
|
4. | B. FILTER HOODS - EXHAUST | ||
1. Reading No. 1, 2, and 3 are taken at the front | 1. | Take Reading No. 1, 2, and 3 on vertical | |
middle, and back of the intake slot. | centerlines. | ||
2. For 8 foot hood sections and less, take three | 2. | Refer to A.2, 3. | |
[3] readings at each of three [3] locations: |
|
|
|
1 foot from each end, and one [1] reading in | C. SUPPLY PLENUM | ||
the middle. | 1. | Reading No. 1 only is used. | |
3. For hood sections over 8 feet in length, take | 2. | Take readings on horizontal centerline of grill. | |
three [3] readings at each of four [4] locations: | 3. | Refer to A.2, 3, but only one reading at each | |
1 foot from each end, and two [2] readings in | location | ||
the middle. |
|
|
|
AVTEC INDUSTRIES INC. 1055 MENDELL DAVIS DR. | JACKSON, MS 39272 [888] |
form no. 14018 1998 AVTEC Industries inc.
27