Step 3
Step 4
Step 5
Step 6
Step 7
Refer to Figure 46. Extend elevation jack extension assembly to 7 ft (2 m) dimension as shown. Raise assembly and secure to forward ground mount beam assembly, using 6 ft (2 m) choker and winch assembly.
Warning: Do not attempt to raise reflector/backstructure if winds exceed 25 mph. Raise reflector/backstructure assembly and align with corresponding elevation jack/panning frame assemblies using tag lines for guidance.
Note: A minimum of three tag lines should be used during high wind conditions. Do not exert force while using the tag lines during reflector installation as this will distort the panel surfaces.
Figure 46
Connect reflector/backstructure pivot assemblies to panning frame assembly.
•Use 7/8 x
Attach tripod pivot assembly to elevation jack assembly.
•Use 7/8 x
Securely tighten mounting hardware on both sides of pivot assembly according to
Install subreflector subassembly.
•Use 3/4 in (19 mm) jam nuts and washers making sure the subreflector is repositioned in the exact location determined at the conclusion of its adjustment.
Secure all hardware.
48 | Installation Procedures |