IDEAL INDUSTRIES BUC5034 manual Instructions for use, Adjusting the timing of the charging pump

Page 17

ASSEMBLY

1.Instructions for use

Regulating the storage temperature of hot water for sanitary systems:

The regulating button A allows for the average temperature of stored sanitary hot water to be adjusted between 10 and 80ºC, with a hard point at 6 (about 60ºC).

In the event of prolonged absence:

In order to ensure that the sanitary hot water tank is protected against frost, set the regulating button A to the position 1 (this setting corresponds to a temperature of about 10ºC).

2.Adjusting the timing of the charging pump

The timing device for stopping the charging pump allows the pump to keep operating for 4 minutes (factory setting) after the setting temperature for the sanitary system has been reached. This allows the residual heat accumulated in the body of the heating unit to be used to complete the reheating of the sanitary hot water.

Adjustment: This timing device can be adjusted from 3 to 6 minutes, with the aid of the potentiometer located on the back of the unit.

Taking the timing device out of operation: To take the timer out of operation, remove the bridge unit located on the back of the device, as shown in the drawing opposite.

3.Adjusting the limiter thermostat

It is possible to change the setting of the limiter thermostat, over a range from 30 to 90ºC, the original setting being 80ºC. To do this:

-Take the module out of the boiler console, if applicable;

-Remove the setting button, by drawing it towards yourself;

-Unhook the PCB;

-Adjust the limiter thermostat in accordance with the reference settings shown in the diagram opposite, with the aid of a flat screwdriver;

-Reassemble the unit by proceeding in the reverse order.

 

23

1

4

 

5

8

67

 

 

 

￿￿￿￿￿￿￿

￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿

 

 

 

A

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TEMPO

￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿￿

 

 

 

 

 

 

 

MINI

MAXI

 

 

 

 

T

 

 

T=0

 

 

 

 

 

90ºC

30ºC

 

 

 

 

 

 

 

 

 

 

 

80ºC

 

 

 

 

 

 

30

C

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

90

C

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

80

C

 

 

 

 

 

 

￿￿￿￿￿￿￿

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5

6

 

 

 

 

 

 

 

 

 

 

4

 

7

 

 

 

 

 

 

 

 

 

3

 

8

 

 

 

 

 

 

 

 

MB

2

 

 

 

 

 

 

 

 

 

 

 

1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.Installation and Connection

For all boilers:

-Remove the TL bridge, connected to the terminal strip of the boiler control console, with terminals 1 and 2 to terminals 1 and 3.

-Withdraw the LP bridge at terminals 4 and 5 in order to do away with an ECS priority.

Main

￿￿

￿￿

￿￿

￿￿

 

Terminal

￿￿￿￿

￿

￿￿￿

￿￿

￿￿￿￿￿￿￿

Strip

 

 

 

 

 

 

 

 

 

-

Remove the panel A from the control console of the boiler

￿

 

￿

 

 

￿

 

￿

￿￿￿￿

 

(refer to the technical instruction plate).

 

 

 

 

 

 

 

￿

-

Connect the connector elements B and C of the module to

 

 

 

 

 

 

 

 

the connectors D and E coming from the boiler control

 

 

 

 

 

 

 

 

console (blue on blue, red on red).

 

 

 

 

 

 

 

-

Attach the earthing wire F to an earthing terminal of the

￿

 

 

 

 

 

 

 

control console.

 

 

 

 

 

 

 

 

 

 

￿

 

 

 

 

￿

 

 

 

 

￿￿

￿

￿

￿￿

￿￿￿￿￿￿￿

 

 

 

￿

 

 

 

 

 

 

 

￿

 

 

 

 

￿￿￿

 

 

 

 

 

 

 

￿

 

 

 

 

 

 

 

 

 

Buccaneer GT, Falcon GTE - Installation, Assembly & Servicing

 

 

 

 

 

 

 

 

17

Image 17
Contents Installation, Assembly and Servicing General Technical Specifications of Combination Boilers Hreaded Main Dimensions Buccaneer GT Combination BoilerFalcon GTE Combination Boiler Assembly Installation Installing the BoilerBoiler Location VentilationConnection of the Domestic Hot Water Circuit InstallationHydraulic Connections Example Buccaneer GT Example of InstallationTools required Assembly Buccaneer GT Combination BoilerAssembling the base and draining tube AssemblyPackage IC1, IC2, IC3 Assembling the boiler onto the tank Installing the pipes Assembling the tank front panelBoiler GTE 4 GTE 5 Assembly Falcon GTE Combination BoilerAssembling the boiler on the hot water tank Installing the tubesAssemble the boiler as instructed in figures 1 Hydraulic Boiler to Tank Connections Kit BH46 AssemblyOperating Principle Assembly ControlsDescription Electrical Connections Fitting and Connecting the MB1 ModuleMB1 Domestic Hot Water Sensor Operating and Installation Package AD127Tank Sensor Boiler SensorAdjusting the limiter thermostat Adjusting the timing of the charging pumpInstallation and Connection Instructions for useSecuring the module Connections Installation with MB1 ModuleHeating and Domestic Hot Water Installation with MB1 module Connecting the BurnerCommissioning Secondary Circuit Assembly CommissioningStarting Up Servicing Maintenance and Periodic Checks Buccaneer GT, Falcon GTE Installation, Assembly & Servicing Buccaneer GT, Falcon GTE Installation, Assembly & Servicing Ideal Installer/Technical Helpline 01482 498