6F8A0870
6. Operation
CAUTION
Do not touch the terminal board when power is supplied.
Touching the terminal board when power is supplied can
DON’T | cause electric shock. |
Do not touch the main body when high temperature fluid is being measured.
The fluid raises the main body temperature and can cause burns.
DON’T
Preparatory check
Follow the procedure described below to prepare before starting the flow measurement (described with regard to the entire flowmeter).
Check the items listed below
Make sure all the bolts of connection flanges on which the flowmeter is mounted securely tightened.
Make sure the direction of flow arrow is in accordance with actual flow.
Make sure the flowmeter is grounded with 100 ohm or less ground resistance.
Make sure the housing covers are securely tightened.
Placing SystemLet the fluid go through the detector pipe. (Note 1)
When the detector is filled with the fluid, stop the fluid and keep it still in the detector pipe.
Supplying Electric PowerMake sure the power supply is as specified.
Checking Converter ParametersCheck the configuration parameter settings. Refer to combined converter's manual.
Zero AdjustmentWait for 30 minutes to warm up the flowmeter. Then making sure the fluid holds still in the detector pipe, starts the zero adjustment. Refer to combined converter's manual.
After checking the items and conducting the zero adjustment as listed above, let the fluid go through the detector pipe. Output
Note 1: If the detector pipe is not filled with the fluid to be measured, the flow rate will be indefinite and unable to be measured. Before using the flowmeter , be sure to fill the detector pipe the fluid to be measured.