1001420 Hose Kit
Verify Control Movements
1.Mount loader to tractor: Remove mount pins from loader uprights. Align tractor with loader and slowly drive tractor into loader. Shut off tractor.
2.Connect loader feedline hoses to the loader control valve quick couplers. See Figure 19.
3.Comply with all safety rules and start the tractor.
4.Mount loader to tractor by activating bucket cylinders to raise or lower the loader uprights into the loader mounts. Slowly drive tractor forward, activating appropriate cylinders to engage loader completely into mounts. Insert mounting pins to secure loader.
5.Check that all tractor hydraulic control lever positions operate the loader movements correctly. See Figure 20.
6.If loader movements do not respond correctly, shut off tractor, relieve pressure, and reconnect properly. Loader control movements must be correct before proceeding.
7.Once all loader functions are correct, start the tractor and operate the loader to check for leaks. Purge any remaining air from the hydraulic system and check oil level.
8.When hose routings and correct loader operations are verified, identify each circuit by placing a matching colored band around the male and female
9.Attach the plastic tie straps (included in kit) every 20 inches around the hoses to keep them tightly bundled and away from contact with the ground or other moving parts on the tractor or loader.
10.Before operating the loader, make sure that the
●Handle forward - Boom down
●Handle forward to limit - Float position
●Handle back - Boom up
●Handle right -
Dump bucket or attachment (slow)
●Handle right to limit -
Dump bucket or attachment (fast)
●Handle to left - Rollback bucket or attachment
Figure 20. Single Lever Control Operation
MAN0064 (Rev. 7/20/2007) | Hydraulic Installation 15 |
|
|