PRE-INSTALLATION

GBC 2064WF-1

Operation Manual

PRE-INSTALLATION

Before a 2064WF-1 Laminator can be installed, ensure the following requirements are met:

1. Are doorways and hallways wide enough for the laminator to be moved to the installation site?

2. Is there ample room for the laminator?

• A work area must be established that allows for operation in both the front and rear of the laminator and provides space for efficient material flow.

3. Is the environment appropriate for the laminator?

• The laminator requires a clean, dust and vapor free environment to operate properly.

• Avoid locating the laminator near sources of heat or cold. Avoid locating the laminator in the direct path of forced, heated or cooled air.

CAUTION: Air flow can cause uneven heating / cooling of the rollers and result in poor output quality.

4. Have you contacted a certified electrician to wire the receptacle and ensure that adequate power is being supplied, having the appropriate capacity, over current protection and safety lockouts available?

GBC 2064WF-1 WF Requires:

• 220V at 60Hz with 40 amps single phase.

• Nema 6-50 P 50 A 250V Receptacle

This Machine is supplied with a Nema 6-50 male plug.

INSTALLATION

1.Shipping damage should be brought to the immediate attention of the delivering carrier.

2.With assistance, carefully roll the laminator into position over flat and even surfaces.

3.The laminator should be positioned to allow exiting film to flow freely to the floor or a work table. Accumulation of laminate immediately behind the laminator as it exits the equipment may cause the film to wrap around the pull rollers, resulting in a “jammed” condition.

4.Avoid locating the laminator near sources of heat or cold. Avoid locating the laminator in the direct path of forced, heated or cooled air.

5.Once the laminator has been properly positioned, lock the castors in place. Locking the castors prevent the machine from rolling during set up, operation or servicing.

6.Connect the attachment plug provided with the laminator to a suitably grounded outlet. Avoid connecting other equipment to the same branch circuit to which the laminator is connected, as this may result in nuisance tripping of circuit breakers or blowing fuses.

Note: Machine must be leveled to ensure best performance. Level the machine by lowering both the main and pull rolls. Lay a level on top of the main and pull rolls. Then, check level from main roll to pull roll on right and left side of the roll. Finally, check by placing the level diagonally across lower main to lower pull rolls.