3.14.Full System Power Up

To complete a full system power up, perform the following steps:

1)Turn OFF all the circuit breakers that supply ac power to the rectifiers in the MX28B DC power plant.

Turn on the external circuit breaker from the battery to the power plant.

Turn on all the circuit breakers that supply AC power to the rectifiers in the MX28B DC power plant.

Load circuit protection may now be enabled as required.

Page 22

MX28B200/400 –48 VDC User’s Manual (990-9133)

Page 28
Image 28
American Power Conversion MX28B200 user manual Full System Power Up