Installation Procedures

Join Adjacent Enclosures and Bolt Enclosures to the Floor

Join adjacent enclosures

To join NetShelter VX Enclosures, see the installation manual included with your enclosures.

See also

Bolt Enclosures to the Floor

Proper anchoring hardware must be in place before starting this procedure.

To bolt the PDU and enclosures to the floor, follow these steps for each enclosure: 1. Remove the front and rear skirts on the enclosure.

2.Insert two bolts through each plate and the holes in the plinth, using the bolt plate (included). Screw the bolts into the pre-installed anchoring hardware in the floor.

3. Tighten the bolts to 81 n·m, using a torque wrench.

InfraStruXure Site Planning, Installation, Start-Up