Site Preparation: Basic Installation Procedure

6.Connect the power source to the PDU.

A licensed electrician must connect the power source.

See page 13 for detailed instructions.

7. Connect user contact inputs and output relays to the user connection plate.

See page 17 for detailed instructions.

8. Install Shielding Troughs, Shielding Partitions, and Cable Ladders.

For instructions, see the manuals included with your Shielding Troughs,

Shielding Partitions, and Cable Ladders.

See also

9.Install the Rack Automatic Transfer Switches (ATS), Rack Power Distribution Units, and other InfraStruXure rack-mount devices.

For instructions, see the manuals included with your Rack ATS, Rack PDU, or other InfraStruXure rack-mount device.

See also

10. Route and attach PDU power cables to each Rack ATS and/or Rack PDU.

See page 22 for detailed instructions.

11. Route and attach communication cables to the InfraStruXure Manager hub (or switch).

See page 27 for detailed instructions.

12.Start the system.

Only qualified, APC-trained personnel may perform a system start-up.

See page 29 for detailed instructions.

13. Configure the InfraStruXure Manager.

For instructions, see the manual included with your InfraStruXure Manager.