| Step 1 | ● Parts Needed For ● | ● 8934 Ramp (1) |
|
| ● 9367 Front Floor Frame (2) |
| ||
| Floor Frame Assemblies | ● 8936 Rear Floor Frame (2) |
| |
| ● 8937 Side Floor Frame (4) |
| ||
| A14 |
|
| |
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
The front floor frame is made up of three pieces. The side floor frames and the rear floor frame are made up of two pieces. The holes in these pieces will align when the pieces are positioned with correct amount of overlap. The illustrations below show the proper overall length for the sides, rear and front. Proceed as follows:
1 Place the front floor frames as
shown. Center the ramp, with drain holes facing outside, on top of the two front floor frames. Join the frames by inserting eight screws.
2 Overlap the side floor frames and
9367
8934
9367
|
| 8937 | 8936 |
|
|
|
|
| |
|
|
|
| |
|
|
| Front Floor | |
| STEP | 8934 | ||
| Frame Assembly | |||
| 1 | |||
|
| 119 3/8" | 3,0m | |
|
| 9367 | 9367 |
|
|
|
|
DRAIN HOLES FACE
OUTSIDE
the rear floor frames as shown. The holes in these pieces will align when the pieces are positioned with cor- rect amount of overlap. See the illus- trations below for the proper overall lengthofthesideandrearfloorframes. Join the frames by inserting four/five bolts into each frame set as shown.
3 Double check the length of each and set these pieces aside for later use.
STEP
2
STEP
3
8937
Side Floor Frame 91 1/8" 2,3m
8937
Rear Floor Frame 119 3/8" 3,0m
89368936
91 1/8" 2,3m
91 1/8" 2,3m
119 3/8" 3,0m
Front & Rear
119 3/8" 3,0m
14