LMBL Series Continued
Brushless Linear Iron Core Servo Motor Continued
Modular Magnet Track |
|
Installation | Refer to Figure |
| recommended procedure to install these modular magnet track sections. |
| Note: It is recommended that rubber coated tool handles be used to reduce injury |
| (pinching fingers etc.) and protect the surface of the magnets. |
1.Bolt the coil assembly onto the underside of the slide (carriage). Ensure the leads extend in the proper direction.
2.Install the magnet track on the
Place a 0.030″ ± 0.005″ thick non magnetic shim on the magnet track. The shim thickness must be equal to the recommended air gap (space between the coil assembly and the magnet track).
Figure 2-3 Modular Magnet Track Installation
|
| Slide |
|
| Coil Assembly |
|
| Rail |
|
| Install one section of magnet track |
Base |
| Move Slide to this side |
| ||
|
| after coil is installed |
3.Hold the slide with a firm grip and move it over the magnet track section/shim.
Note: The slide will be drawn forcefully towards the magnet track and may overshoot the rails if not held firmly.
Check the space between the shim and the coil assembly. If the space between the shim and the coil assembly is large, uniformly loosen the mounting screws allowing the coil assembly to be fully and evenly lowered onto the shim. Insert another shim thick enough to fill the gap between the coil assembly and the slide, see Figure
Figure 2-4 Air Gap Adjustment
Slide | Shim |
| |
Coil Assembly | (if necessary) |
|
Rail | Air Gap (0.30± 0.005) |
|