Replacing the Supervisor Engine

Figure 14 DC-Input Wire Connections on the Terminal Block

48V INPUT 1

+

GND

INPUT POWER

GOOD

RTN

-48vdc GND

 

 

105085

 

 

 

Warning

When installing or replacing the unit, the ground connection must always be made first and

 

 

disconnected last. Statement 1046

 

 

Step 5

After ensuring that all wire connections are secure, reinstall the terminal block cover.

 

 

 

Replacing the Supervisor Engine

Before you can power up the system, you need to remove the supervisor engine from slot 1 (if a redundant supervisor engine is present, remove it from slot 2) and install the Supervisor Engine 720 or the Supervisor Engine 32 in slot 5 or 6.

Removing the Supervisor Engine

This section describes how to remove an existing supervisor engine from a chassis slot.

To remove a supervisor engine from the chassis, perform these steps:

Step 1 Disconnect any network interface cables attached to the supervisor engine.

Step 2 Verify that the captive installation screws on all of the modules in the chassis are tight. This step assures that the space created by the removed supervisor engine is maintained.

Note If the captive installation screws are loose, the electromagnetic interference (EMI) gaskets on the installed modules will push the modules toward the open slot, reducing the opening size and making it difficult to install the replacement module.

Catalyst 6509-NEB Switch and Cisco OSR-7609 Router Upgrade Note

 

78-16162-02

17

 

 

 

Page 17
Image 17
Cisco Systems OSR-7609, 6509-NEB manual Replacing the Supervisor Engine, Removing the Supervisor Engine