Cisco Systems manual 2-14, 9 C Brackets for the Cisco MDS 9200 Series Close-Up View

Models: MDS 9200 Series

1 164
Download 164 pages 61.43 Kb
Page 70
Image 70
Figure 2-9 C Brackets for the Cisco MDS 9200 Series (Close-Up View)

Chapter 2 Installing the Cisco MDS 9200 Series

Installing the Switch in a Cabinet with Insufficient Front Clearance

Se n d d o c u m e n t a t i o n c o m m e n t s t o m d s f e e d b a ck - d o c @ c i s c o . c o m

Figure 2-9 C Brackets for the Cisco MDS 9200 Series (Close-Up View)

94297

Note Ensure the C bracket is oriented so that it blocks the fewest airflow holes on the chassis; the holes should be slightly closer to the bottom of the brackets and the text on the back of the bracket should be right side up.

b.Repeat with the other C bracket on the other side of the switch.

Installing Front Rack-Mount Brackets for Cabinets with Less Than 26 Inches of Rail Spacings

The front rack-mount brackets for the Cisco MDS 9200 Series switch must be installed onto the switch prior to installing the switch into the cabinet. For cabinets with less than 26 inches of rail-to-rail spacing, the front rack-mount bracket must be installed 180 degrees from normal. To install the brackets for cabinets with front-mounting rail to rear-mounting rail spacing of less than 26 inches that need to be mounted backwards to maintain adequate fiber-optic clearance, follow these steps:

Step 1 Install the front rack-mount brackets as follows:

a.Position one of the front rack-mount brackets against the side of the switch and align the screw holes as shown in Figure 2-10. Then attach the bracket to the switch with the six M4 screws originally provided with the bracket.

 

Cisco MDS 9200 Series Hardware Installation Guide

2-14

OL-17468-02

Page 70
Image 70
Cisco Systems manual 2-14, 9 C Brackets for the Cisco MDS 9200 Series Close-Up View