Setting Up and Installing the GbE Interconnect Switch

2.Slide the GbE Interconnect Switch into the right communication bay in the front side of the ProLiant BL p-Class server blade enclosure (1).

3.Lock the ejector lever (2).

1

2

Figure 2-2: Installing the GbE Interconnect Switches

4.Repeat steps 2 and 3 for the second GbE Interconnect Switch in the left communication bay.

IMPORTANT: Be sure that the interconnect modules are fully seated. The latch/handle will drop into place when the module is firmly seated.

Replacing an Existing GbE Interconnect Switch

CAUTION: Removing an RJ-45 Patch Panel from a powered enclosure will result in the loss of network communications between the server blade and the network infrastructure.

IMPORTANT: If you are replacing an existing GbE Interconnect Switch or upgrading from an RJ-45 Patch Panel, and have strict security requirements:

Do not cable the GbE Interconnect Switch until after configuration. Or

Connect the GbE Interconnect Switch to the optional Diagnostic Station. The Diagnostic Station enables you to power up, configure, and diagnose a ProLiant p-Class server blade or a ProLiant p-Class GbE Interconnect Switch outside of the rack environment.

To replace an existing GbE Interconnect Switch:

1.If possible, save the configuration file to a TFTP server for later retrieval. Refer to the “Saving Settings to a TFTP Server” section in Chapter 3 (console management interface) and “Saving Settings to TFTP Server” in Chapter 4 (Web-based management interface).

2.On the front side of the ProLiant BL p-Class server blade, release the ejector lever for the GbE Interconnect Switch.

3.Pull down on the ejector lever to unlock the GbE Interconnect Switch from the enclosure.