Installation & Operation Manual

5 Hydronic piping

Near boiler piping components

1.

Boiler piping:

 

Boiler system piping should be sized per the pipe

 

requirements listed in Tables 5A and 5C.

2.

Boiler circulating pump:

 

Field supplied. When using Primary/Secondary piping the

 

boiler circulating pump should be sized per Table 5A.

3.

Hot Water Generator circulating pump:

 

Field supplied. When installed in a Primary/Secondary

 

arrangement, the Crest requires an additional pump for

NOTICE

A system supply sensor (factory supplied)

MUST BE installed with Primary/Secondary

 

 

systems for proper boiler operation.

10.Y-Strainer:

Field supplied. A Y-strainer or equivalent multipurpose strainer is recommended at the inlet of the heat exchanger to remove system particles from older hydronic systems and protect newer systems.

the Hot Water Generator Loop. The pump should

be sized per Table 5A. Consult the indirect water

heater operating guide to determine flow characteristics

for the selected product used. The pump’s total flow and

heat requirements are the sum of the boiler and the indirect

water heater.

4. Boiler isolation valves:

Field supplied. Full port valves are required. Failure

to use full port valves could result in a restricted flow

rate through the boiler.

￿CAUTION

NOTICE

The maximum allowable water flow rate through a single Crest boiler is 350 GPM. Exceeding this flow rate will result in damage to the heat exchanger and/or piping.

Reference Table 5B1 for the minimum recommended flow rate through a single Crest boiler at full fire to maintain a 80°F temperature rise. Reference Table 5B2 for the absolute minimum flow rate through a single Crest boiler.

5.

Check valves:

 

 

 

 

Field supplied. Check valves are required for

 

installation as shown in FIG.’s 5-2 and 5-3. Failure to

 

install check valves could result in a reverse flow

 

condition during pump(s) off cycle.

 

6.

Domestic indirect hot water isolation valves:

 

Field supplied. Full port valves are required. Failure to use

 

full port valves could result in a restricted flow rate through

 

the boiler.

 

 

 

7.

Anti-scald mixing valve:

 

 

Field supplied.

An anti-scald mixing valve is

 

recommended when storing domestic hot water above

 

115°F (46°C).

 

 

 

8.

Pressure relief valve:

 

 

 

Factory supplied. The pressure relief valve is sized to

 

ASME specifications.

 

 

 

9.

System temperature sensor:

 

 

Lochinvar supplies

a

system

temperature sensor.

 

The sensor is to be installed in the heating loop

 

downstream from the boiler hot water piping and

 

heating loop junction.

The

sensor should be

 

located far enough downstream to sense system diluted

 

water temperature.

 

 

 

Table 5B1 Minimum Flow Rate with the Boiler at Full Fire

TEMPERATURE RISE APPLICATIONS

MODEL

FLOW RATE (GPM)

 

 

FB(N,L)1500

35

 

 

FB(N,L)2000

46

 

 

FB(N,L)2500

58

 

 

FB(N,L)3000

70

 

 

FB(N,L)3500

81

 

 

[Based on 80°F Temperature Rise]

Table 5B2 Absolute Minimum Flow Rate

ABSOLUTE MINIMUM FLOW RATE

MODEL

FLOW RATE (GPM)

 

 

FB(N,L)1500

25

 

 

FB(N,L)2000

25

 

 

FB(N,L)2500

25

 

 

FB(N,L)3000

25

 

 

FB(N,L)3500

45

 

 