INSTALLING LOG SET AND SCREEN

22

INSTALLATION

Optional Wall Mounted Thermostat - GWMT1 [Remote-Ready Models Only] (Cont.) Optional Wall Switch - GWMS2 [Remote-Ready Models Only]

Installing Log Set and Screen

INSTALLATION

Continued

6.Connect one bare wire end to each terminal (“W” and “R”) of the thermostat base (see Figure 43).

7.Install the base onto the wall with the provided screws.

8.Move the temperature adjustment back and forth to insure the bimetal is free from restrictions.

9.Replace the cover onto the base. (Upon installation, the ther- mostat must be allowed to stabilize at room temperature for a minimum of 30 minutes for proper operation).

10.Set switch on fireplace to Auto position.

11.Set the temperature adjustment to the desired setting. This ther- mostat has been electronically calibrated at the factory. No ad- justment or leveling is necessary.

Feed wires through rectangular slots

Figure 42 - Back View of Thermostat Base

Terminal “W”

W

Terminal “R”

R

Manual background WARNING: Do not connect this switch to any electrical source! Electrical shock and/or fire hazard will occur.

1.Connect one terminal of 25 ft. wire to bottom contact of switch (see Figure 41, page 21).

2.Connect remaining wire terminal to the “TH” terminal on the control valve. Make sure that wire terminals are in the posi- tions on your unit as pictured in Figure 41, page 21. If wires are not “crossed” the thermostat will not work.

3.Route the 25 ft. wire to a convenient location to mount your wall switch (no outside walls).

Manual background WARNING: Do not connect the switch to a power source. Electrical shock and/or fire hazard will occur.

IMPORTANT: The wire may be shortened but must not be lengthened.

4.Connect one bare wire end to each of the terminals of the pro- vided wall switch.

5.Install the wall switch and cover in the wall.

INSTALLING LOG SET AND SCREEN

1.Remove log packaging material and discard packaging. Gen- tly place log on burner support (see Figure 44). The log should fit flat against top of burner support and log locator tabs fit into the slots under the log. Do not allow log to contact flame. If flame contacts log, soot will be created.

2.Reattach screen by placing the notches in the screen frame over the shoulder screws and pushing down.

Shoulder Screw

Log

Figure 43 - Thermostat Base Terminals “W” and “R”

OPTIONAL WALL SWITCH - GWMS2 (Remote-Ready Models Only)

Manual background WARNING: Read and follow installation instruc- tions. Installation should be done by a qualified installer familiar with low-voltage wiring procedures.

Screen

Burner Support with

Log Locator Tabs

Figure 44 - Installing Log and Screen

Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundForManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background.Manual backgroundManual backgroundManual backgroundManual background.comManual backgroundManual backgroundManual backgroundManual backgroundManual background

107032-01F

Page 22
Image 22
Desa VMH10TNB, EFS26PR, VMH26PRA, VMH26NRA installation manual Installing Log Set And Screen, Installation, Continued